SWITCH,LIMIT,MODEL ZQ158,PTFE
Material 4100053615 · SWITCH · Plant 1000
ASafety-criticalLong-leadMonitorSlow-moving
- Material
- 4100053615
- Category
- SWITCH
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (11 of 29 FuncLocs A/B, 22 safety/shutdown valve)
- Supplier
- MEGA TEKNIK MAKMUR PT
- Lead time
- 88 d · P80 152 d
- Unit price
- Rp 3.0M
Recommendation
- 1.Safety-critical element: installed on 22 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 2.5 EA/year: 2.5 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~88 days; expected demand during lead time 0.6.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 8.
- 5.Long lead time: 80% of deliveries took up to 152 days and the fastest seen in its category 32 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 29 FuncLoc(s), 11 of them criticality A/B.
- 7.ML early warning: 60% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningSingle sourceOpen PO
On hand / on order
7 / 2
next delivery 07 Oct 2026
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
8
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 3.0M
PO history
ML early warning: 60% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 273 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~32 days.
Installed on 29 functional locations
11 with criticality A/B · 43 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_SDV-289 C4 PRODUCT ISOLATION | A | 1 | 2 | 0.48 |
| PX_SDV-1325A DILUTION STEAM ISOLATION | A | 1 | 1 | 0.06 |
| PY_SDV-1973A VD-694 SHUTDOWN VALVE | A | 4 | 1 | 0.06 |
| PX_SDV-955A FUEL OIL ISOLATION | A | 1 | 0 | 0.06 |
| PX_PP-1865A-CSS CONTROL SWITCH STATION FOR PP-1865A-M | B | 1 | 1 | 0.62 |
| PX_MOV-1696 MOTOR OPERATED GATE VALVE | B | 1 | 0 | 0.06 |
| PX_PP-1862-CSS CONTROL SWITCH STATION FOR PP-1862-M | B | 1 | 0 | 0.19 |
| PX_PP-410-CSS CONTROL SWITCH STATION FOR PP-410-M | B | 1 | 0 | 0.19 |
| PX_SDV-142 ON-OFF VALVE | B | 4 | 0 | 0.06 |
| PX_SDV-668 LUBE OIL ISOLATION | B | 1 | 0 | 0.06 |
| PX_SDV-742A METHANOL ISOLATION | B | 1 | 0 | 0.06 |
| PX_PP-1838D-CSS CONTROL SWITCH STATION FOR PP-1838D-M | C | 4 | 0 | 0.19 |
Lead time and procurement
Lead time 88 ± 42 days (PO history, 4 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 24 Jul 2026 | PR03 Regular replenishment | 1 | Rp 2.9M | 16 Dec 2026 open | 145 d |
| 20 Jul 2026 | PR06 Regular replenishment | 1 | Rp 3.1M | 07 Oct 2026 open | 79 d |
| 19 Jun 2025 | PR06 Regular replenishment | 2 | Rp 3.0M | 06 Aug 2025 | 48 d |
| 13 Jun 2025 | PR06 Regular replenishment | 3 | Rp 2.9M | 22 Nov 2025 | 162 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 06 Aug 2026 | Medium | PX_SDV-737C | SDV-737C solenoid burnt |
| 02 Feb 2026 | Low | PX_SDV-289 | Replace lamp as per PM finding |
| 13 Aug 2025 | Medium | PX_SDV-200A | Painting SDV-200A |
| 04 Jul 2025 | Medium | PX_SDV-200A | SDV-200A solenoid burnt |
| 27 Jun 2025 | Medium | PX_SDV-289 | Install scaffolding at SDV-289 |
| 20 Jun 2025 | Medium | PX_PP-1865A-CSS | Replace lamp as per PM finding |
| 30 May 2025 | Low | PY_SDV-1973A | SDV-1973A limit switch faulty |
| 21 May 2025 | Low | PX_SDV-277 | Install scaffolding at SDV-277 |
| 18 May 2025 | Medium | PX_SDV-737C | Leak from packing |
| 14 May 2025 | Low | PX_SDV-1325A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 01 Jan 2026 | 2 | 201000026947 | Corrective |
| 23 Oct 2025 | 1 | 201000022626 | Corrective |
| 26 Aug 2025 | 1 | 201000037542 | Corrective |
| 23 May 2025 | 1 | 201000022889 | Corrective |
| 23 May 2025 | 1 | 205000029984 | Other maintenance |