SWITCH,LIMIT,SIZE CU419,PTFE

Material 4100053659 · SWITCH · Plant 1000

ASafety-criticalLong-leadReorderCriticalStockout
Material
4100053659
Category
SWITCH
Base unit
EA
MRP type
Non Stock
Criticality
A (4 of 9 FuncLocs A/B, 7 safety/shutdown valve)
Supplier
DUTA MANDIRI MAKMUR PT
Lead time
62 d · P80 112 d
Unit price
Rp 2.8M

Recommendation

  • 1.Safety-critical element: installed on 7 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~62 days; expected demand during lead time 0.2.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
  • 6.Long lead time: 80% of deliveries took up to 112 days and the fastest seen in its category 32 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 9 FuncLoc(s), 4 of them criticality A/B.
  • 8.ML early warning: 40% probability of demand in the next 90 days.
Proposed purchase requisition
5 EA
Rp 14.0M · order by 01 Oct 2026
Expected arrival ≈ 62 days
Safety-critical (SCE)Long-leadML early warningSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 11%
Unit price
Rp 2.8M
PO history
ML early warning: 40% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 379 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 477.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~32 days.

Installed on 9 functional locations

4 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_SDV-1929A
VD-890A SHUTDOWN VALVE
A100.06
PX_SDV-958
CL-1833 SHUTDOWN VALVE
A100.06
PY_PP-1862B-CSS
CONTROL SWITCH STATION FOR PP-1862B-M
B100.19
PY_SDV-695
ON-OFF VALVE
B100.06
PX_SDV-1298
METHANOL ISOLATION
S110.48
PX_SDV-445
FUEL OIL ISOLATION
S110.48
PX_SDV-207
ON-OFF VALVE
S100.06
PX_SDV-224
PP-1720D SHUTDOWN VALVE
S100.06
PY_MOV-603
MOTOR OPERATED GATE VALVE
S300.06

Lead time and procurement

Lead time 62 ± 27 days (PO history + category, 2 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
01 Jul 2026PR06
Regular replenishment
1Rp 2.8M22 Sept 202683 d
13 Oct 2025PR06
Regular replenishment
1Rp 2.8M01 Dec 202549 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Jul 2025LowPX_SDV-1298Leak from packing
15 Jul 2025HighPX_SDV-445SDV-445 limit switch faulty

Recent goods issues

Posting dateQtyOrderOrder type
17 Sept 20252201000023016Corrective
16 Sept 20251201000023016Corrective