SWITCH,LIMIT,SIZE CU419,PTFE
Material 4100053659 · SWITCH · Plant 1000
ASafety-criticalLong-leadReorderCriticalStockout
- Material
- 4100053659
- Category
- SWITCH
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 9 FuncLocs A/B, 7 safety/shutdown valve)
- Supplier
- DUTA MANDIRI MAKMUR PT
- Lead time
- 62 d · P80 112 d
- Unit price
- Rp 2.8M
Recommendation
- 1.Safety-critical element: installed on 7 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~62 days; expected demand during lead time 0.2.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
- 6.Long lead time: 80% of deliveries took up to 112 days and the fastest seen in its category 32 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 9 FuncLoc(s), 4 of them criticality A/B.
- 8.ML early warning: 40% probability of demand in the next 90 days.
Proposed purchase requisition
5 EA
Rp 14.0M · order by 01 Oct 2026
Expected arrival ≈ 62 days
Safety-critical (SCE)Long-leadML early warningSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 11%
Unit price
Rp 2.8M
PO history
ML early warning: 40% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 379 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 477.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~32 days.
Installed on 9 functional locations
4 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_SDV-1929A VD-890A SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PX_SDV-958 CL-1833 SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PY_PP-1862B-CSS CONTROL SWITCH STATION FOR PP-1862B-M | B | 1 | 0 | 0.19 |
| PY_SDV-695 ON-OFF VALVE | B | 1 | 0 | 0.06 |
| PX_SDV-1298 METHANOL ISOLATION | S | 1 | 1 | 0.48 |
| PX_SDV-445 FUEL OIL ISOLATION | S | 1 | 1 | 0.48 |
| PX_SDV-207 ON-OFF VALVE | S | 1 | 0 | 0.06 |
| PX_SDV-224 PP-1720D SHUTDOWN VALVE | S | 1 | 0 | 0.06 |
| PY_MOV-603 MOTOR OPERATED GATE VALVE | S | 3 | 0 | 0.06 |
Lead time and procurement
Lead time 62 ± 27 days (PO history + category, 2 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Jul 2026 | PR06 Regular replenishment | 1 | Rp 2.8M | 22 Sept 2026 | 83 d |
| 13 Oct 2025 | PR06 Regular replenishment | 1 | Rp 2.8M | 01 Dec 2025 | 49 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Jul 2025 | Low | PX_SDV-1298 | Leak from packing |
| 15 Jul 2025 | High | PX_SDV-445 | SDV-445 limit switch faulty |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 17 Sept 2025 | 2 | 201000023016 | Corrective |
| 16 Sept 2025 | 1 | 201000023016 | Corrective |