Material 4100054058 · SWITCH · Plant 1000

ASafety-criticalLong-leadMonitorSlow-moving
Material
4100054058
Category
SWITCH
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 4 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
ANUGRAH TEKNOLOGI INTERNASIONAL PT
Lead time
99 d · P80 112 d
Unit price
Rp 3.0M

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~99 days; expected demand during lead time 0.1.
  • 4.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 5.Long lead time: 80% of deliveries took up to 112 days and the fastest seen in its category 32 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
1 / 2
next delivery 12 Jan 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 3.0M
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 223 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 201.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~32 days.

Installed on 4 functional locations

2 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_SDV-1973A
VD-694 SHUTDOWN VALVE
A110.06
PX_MOV-720
MOTOR OPERATED GATE VALVE
A100.06
PX_SDV-145
PP-103 SHUTDOWN VALVE
S100.06
PX_SDV-1554
ON-OFF VALVE
S100.06

Lead time and procurement

Lead time 99 ± 27 days (PO history + category, 2 PO lines) · on-time 23%

PR dateTypeQtyUnit priceDeliveryLead time
30 Aug 2026PR03
Regular replenishment
2Rp 3.0M12 Jan 2027
open
135 d
30 Aug 2025PR06
Regular replenishment
1Rp 3.0M27 Feb 2026181 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 May 2025LowPY_SDV-1973ASDV-1973A limit switch faulty

Recent goods issues

Posting dateQtyOrderOrder type
20 Feb 20261201000016647Corrective