SWITCH,LIMIT,SIZE GK804,NBR
Material 4100054163 · SWITCH · Plant 1000
ASafety-criticalReduceNon-moving
- Material
- 4100054163
- Category
- SWITCH
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B, 3 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 60 d · P80 112 d
- Unit price
- Rp 6.0M (est.)
Recommendation
- 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
- 3.Lead time ~60 days; expected demand during lead time 0.0.
- 4.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
- 5.Stock 12 exceeds the level to keep (2) by 10.
- 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
12 / 0
no open PO
Today Min / Max
5 / 14
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 6.0M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~32 days.
Installed on 4 functional locations
2 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_SDV-1325A DILUTION STEAM ISOLATION | A | 1 | 1 | 0.06 |
| PX_PP-1366A-CSS CONTROL SWITCH STATION FOR PP-1366A-M | A | 1 | 0 | 0.19 |
| PX_SDV-1848 HE-1348 SHUTDOWN VALVE | S | 1 | 2 | 0.06 |
| PY_SDV-968A ON-OFF VALVE | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 60 ± 27 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 11 Sept 2026 | Low | PX_SDV-1848 | Install scaffolding at SDV-1848 |
| 18 May 2025 | Medium | PX_SDV-1848 | Leak from packing |
| 14 May 2025 | Low | PX_SDV-1325A | Leak from packing |
Recent goods issues
Never issued in the 17-month history.