TRANSMITTER,PRESS,MODEL DY707,INCOLOY
Material 4100055430 · TRANSMITTER · Plant 1000
ALong-leadReduceExcess
- Material
- 4100055430
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (29 of 68 FuncLocs A/B)
- Supplier
- SAMUDRA MESINDO ABADI PT
- Lead time
- 76 d · P80 107 d
- Unit price
- Rp 43.2M
Recommendation
- 1.Forecast 15 EA/year: 15 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~76 days; expected demand during lead time 3.1.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 14.
- 4.Stock 756 exceeds the level to keep (14) by 742.
- 5.Long lead time: 80% of deliveries took up to 107 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 68 FuncLoc(s), 29 of them criticality A/B.
- 7.ML early warning: 73% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceAbnormal consumptionOpen PO
On hand / on order
756 / 9
next delivery 13 Dec 2026
Today Min / Max
15 / 28
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 8
Rec. Max
14
order qty 3
Service level
99.8%
stockout risk now 0%
Unit price
Rp 43.2M
PO history
ML early warning: 73% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 104 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Lumpy · 17 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 8.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 68 functional locations
29 with criticality A/B · 96 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_DPT-956-2A DIFF. PRESSURE | A | 1 | 4 | 1.35 |
| PX_TIT-680-43B HE-1522 TEMPERATURE | A | 3 | 2 | 0.04 |
| PX_FIT-600-3B PP-287D INLET FLOW | A | 1 | 1 | 0.04 |
| PX_DPT-1291-5B VD-185 DP | A | 1 | 0 | 0.06 |
| PX_DPT-462A KC-671D DP | A | 1 | 0 | 0.06 |
| PX_FIT-1125A FLUSHING OIL FLOW | A | 2 | 0 | 0.04 |
| PX_FIT-1560A SLOP OIL FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-1842 FLOW | A | 4 | 0 | 0.04 |
| PX_FIT-1992A-33B PP-1751A INLET FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-921B FLUSHING OIL FLOW | A | 1 | 0 | 0.04 |
| PX_LIT-805 LEVEL | A | 1 | 0 | 0.03 |
| PX_PIT-1005 RICH AMINE PRESSURE | A | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 76 ± 35 days (PO history, 9 PO lines) · on-time 20%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 19 Sept 2026 | PR06 Regular replenishment | 9 | Rp 44.5M | 13 Dec 2026 open | 85 d |
| 22 Jul 2026 | PR06 Regular replenishment | 15 | Rp 44.2M | 28 Sept 2026 | 68 d |
| 24 Apr 2026 | PR03 Regular replenishment | 14 | Rp 41.2M | 29 Jun 2026 | 66 d |
| 23 Apr 2026 | PR06 Regular replenishment | 10 | Rp 41.7M | 15 Jun 2026 | 53 d |
| 19 Feb 2026 | PR03 Regular replenishment | 14 | Rp 44.0M | 20 Mar 2026 | 29 d |
| 12 Oct 2025 | PR04 Regular (other) | 12 | Rp 41.4M | 24 Jan 2026 | 104 d |
| 09 Sept 2025 | PR06 Regular replenishment | 6 | Rp 43.0M | 29 Oct 2025 | 50 d |
| 04 Jun 2025 | PR03 Regular replenishment | 15 | Rp 43.3M | 06 Oct 2025 | 124 d |
| 25 May 2025 | PR03 Regular replenishment | 15 | Rp 43.2M | 14 Sept 2025 | 112 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_PIT-997A-18 | Replace lamp as per PM finding |
| 09 Sept 2026 | High | PX_TIT-1562 | TIT-1562 error |
| 21 Aug 2026 | Low | PX_DPT-956-2A | DPT-956-2A abnormal indication |
| 16 Jul 2026 | Medium | PX_PIT-794A | Install cover plate for MCP cracking |
| 17 Jun 2026 | Medium | PX_DPT-956-2A | Leak from packing |
| 14 Jun 2026 | Medium | PX_FIT-1027-48 | FIT-1027-48 error |
| 05 Jun 2026 | High | PX_TIT-680-43B | Install scaffolding at TIT-680-43B |
| 02 Jun 2026 | Medium | PX_TIT-173B-42 | TIT-173B-42 abnormal indication |
| 23 Apr 2026 | Medium | PX_DPT-386 | Replace lamp as per PM finding |
| 22 Sept 2025 | Low | PX_TIT-173B-42 | TIT-173B-42 abnormal indication |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Jun 2026 | 1 | 201000017456 | Corrective |
| 18 Jun 2026 | 3 | 201000024332 | Corrective |
| 17 Jun 2026 | 1 | 201000024332 | Corrective |
| 31 Mar 2026 | 1 | 204000023773 | Preventive |
| 25 Feb 2026 | 1 | 201000016387 | Corrective |
| 31 Jan 2026 | 1 | 201000001515 | Corrective |
| 31 Jan 2026 | 1 | 201000001793 | Corrective |
| 31 Jan 2026 | 2 | 201000004172 | Corrective |
| 30 Jan 2026 | 1 | 201000024383 | Corrective |
| 25 Jan 2026 | 1 | 201000008178 | Corrective |
| 18 Jan 2026 | 1 | 201000015987 | Corrective |
| 28 Dec 2025 | 2 | 201000005329 | Corrective |
| 18 Dec 2025 | 2 | 201000028633 | Corrective |
| 04 Dec 2025 | 1 | 204000007693 | Preventive |
| 28 Nov 2025 | 3 | 201000006855 | Corrective |