TRANSMITTER,PRESS,TYPE JZ960,CS

Material 4100055535 · TRANSMITTER · Plant 1000

ALong-leadReduceExcess
Material
4100055535
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 13 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
71 d · P80 92 d
Unit price
Rp 21.3M

Recommendation

  • 1.Forecast 6.8 EA/year: 6.8 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~71 days; expected demand during lead time 1.3.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 4.Stock 17 exceeds the level to keep (9) by 8.
  • 5.Long lead time: 80% of deliveries took up to 92 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 13 FuncLoc(s), 3 of them criticality A/B.
  • 7.ML early warning: 58% probability of demand in the next 90 days.
Long-leadML early warningSingle source
On hand / on order
17 / 0
no open PO
Today Min / Max
3 / 7
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
9
order qty 3
Service level
99.8%
stockout risk now 0%
Unit price
Rp 21.3M
PO history
ML early warning: 58% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 71 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 10 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 13 functional locations

3 with criticality A/B · 16 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_DPT-1557A
DIFF. PRESSURE
A1123.92
PX_FIT-729
FLOW
A410.47
PX_PIT-1521C
QUENCH OIL PRESSURE
B100.04
PX_FIT-1842-47B
KC-145 INLET FLOW
C130.90
PX_TIT-462-53A
PP-1751A TEMPERATURE
C120.04
PX_LIT-619A
LEVEL
C100.03
PX_PIT-1369-21B
VD-727 PRESSURE
C100.04
PX_DPT-145
HE-224C DP
S100.06
PX_LIT-447
HE-1766D LEVEL
S100.03
PX_LIT-789-14
HE-1590B LEVEL
S100.03
PX_PIT-210-19A
FEED PRESSURE
S100.04
PX_TIT-1722B
VD-1730 TEMPERATURE
S100.04

Lead time and procurement

Lead time 71 ± 37 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
01 Jan 2026PR03
Regular replenishment
3Rp 21.2M26 Mar 202684 d
28 Oct 2025PR03
Regular replenishment
3Rp 21.9M09 Dec 202542 d
05 Oct 2025PR03
Regular replenishment
6Rp 21.3M17 Jan 2026104 d
04 Jun 2025PR03
Regular replenishment
3Rp 21.4M17 Jul 202543 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Sept 2026MediumPX_DPT-1557AInstall scaffolding at DPT-1557A
10 Aug 2026MediumPX_DPT-1557ALeak from packing
05 Aug 2026LowPX_DPT-1557ADPT-1557A reading frozen
18 Jul 2026MediumPX_FIT-1842-47BFIT-1842-47B reading frozen
08 Jul 2026LowPX_DPT-1557ARepair insulation DPT-1557A
23 Jun 2026MediumPX_DPT-1557AAR25/tranmsitter low performance
20 Jun 2026MediumPX_DPT-1557A[MSI-B-26-PMN-328] Permanent repair
04 May 2026MediumPX_FIT-1842-47BLeak from packing
27 Jan 2026LowPX_DPT-1557ALeak from packing
17 Dec 2025LowPX_DPT-1557ALeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
22 Jul 20261201000023386Corrective
21 Jul 20262201000023386Corrective
24 Jun 20261204000013750Preventive
05 Jan 20261201000025848Corrective
22 Dec 20251201000011542Corrective
08 Dec 20251201000028561Corrective
04 Nov 20251201000010987Corrective
02 Nov 20251201000010987Corrective
09 Oct 20251201000025699Corrective
08 Oct 20251201000025699Corrective