TRANSMITTER,PRESS,SIZE IG306,SS304
Material 4100055552 · TRANSMITTER · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100055552
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 12 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 122 d · P80 126 d
- Unit price
- Rp 30.9M
Recommendation
- 1.Forecast 3.3 EA/year: 3.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~122 days; expected demand during lead time 1.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 8.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 6 now.
- 5.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 12 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 185.7M · order by 01 Oct 2026
Expected arrival ≈ 122 days
Long-leadSingle source
On hand / on order
2 / 0
no open PO
Today Min / Max
3 / 5
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
8
order qty 2
Service level
99.9%
stockout risk now 18%
Unit price
Rp 30.9M
PO history
ML early warning: 27% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 200 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 12 functional locations
6 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PIT-774-28A PRESSURE | A | 1 | 1 | 0.04 |
| PX_FIT-1842 FLOW | A | 1 | 0 | 0.04 |
| PX_LIT-893 CL-1681 LEVEL | A | 1 | 0 | 0.03 |
| PX_PIT-1005 RICH AMINE PRESSURE | A | 1 | 0 | 0.04 |
| PX_PIT-1298-23A PRESSURE | A | 1 | 0 | 0.04 |
| PX_PIT-1593 PRESSURE | A | 1 | 0 | 0.04 |
| PX_PIT-1358-19 CL-816 PRESSURE | C | 1 | 0 | 0.04 |
| PX_DPT-1236-23A DIFF. PRESSURE | S | 1 | 0 | 0.06 |
| PX_LIT-1297A LEVEL | S | 1 | 0 | 0.03 |
| PX_LIT-1841 LEVEL | S | 1 | 0 | 0.03 |
| PX_PIT-1333-39 PP-1811A PRESSURE | S | 1 | 0 | 0.04 |
| PX_TIT-1745 CL-962 TEMPERATURE | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 122 ± 45 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 10 Nov 2025 | PR04 Regular (other) | 2 | Rp 31.5M | 05 May 2026 | 176 d |
| 30 May 2025 | PR04 Regular (other) | 2 | Rp 30.4M | 27 Dec 2025 | 211 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 10 May 2025 | High | PX_PIT-774-28A | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Mar 2026 | 1 | 204000017829 | Preventive |
| 14 Feb 2026 | 1 | 201000033319 | Corrective |
| 13 Feb 2026 | 1 | 201000033319 | Corrective |
| 24 Dec 2025 | 2 | 201000007346 | Corrective |
| 20 Dec 2025 | 2 | 201000035634 | Corrective |