TRANSMITTER,PRESS,TYPE UV257,SS304

Material 4100055566 · TRANSMITTER · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100055566
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 8 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
71 d · P80 126 d
Unit price
Rp 66.1M

Recommendation

  • 1.Forecast 3.1 EA/year: 3.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~71 days; expected demand during lead time 0.6.
  • 3.A 99.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 2 now.
  • 5.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 8 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
2 EA
Rp 132.3M · order by 01 Oct 2026
Expected arrival ≈ 71 days
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.0%
stockout risk now 1%
Unit price
Rp 66.1M
PO history
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 227 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 8 functional locations

1 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PIT-1253
QUENCH OIL PRESSURE
A100.04
PX_DPT-817A-1
DIFF. PRESSURE
C420.92
PX_FIT-1918A-48
FLOW
C100.04
PX_LIT-867B-17B
HE-1783 LEVEL
C100.03
PX_PIT-1803-43
PRESSURE
C100.04
PX_DPT-386
PP-1991A DP
S130.92
PX_FIT-1177A-1
FLOW
S100.04
PY_LIT-431A
KC-891A LEVEL
S100.03

Lead time and procurement

Lead time 71 ± 45 days (PO history + category, 2 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
20 Jul 2026PR06
Regular replenishment
2Rp 65.3M13 Aug 202624 d
14 Jul 2025PR03
Regular replenishment
4Rp 67.0M02 Nov 2025111 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Apr 2026MediumPX_DPT-386Replace lamp as per PM finding
11 Mar 2026HighPX_DPT-817A-1Check DPT-817A-1.ok
11 Sept 2025MediumPX_DPT-386[MSI-B-25-DXF-173/M] Replace line
04 Jun 2025MediumPX_DPT-817A-1Leak from packing
24 May 2025MediumPX_DPT-386AR25/tranmsitter low performance

Recent goods issues

Posting dateQtyOrderOrder type
16 Feb 20261201000003542Corrective
15 Feb 20261201000003542Corrective
11 Dec 20252201000005250Corrective
22 Nov 20252204000021668Preventive
14 Oct 20251201000031460Corrective