TRANSMITTER,PRESS,TYPE UD152,SS304

Material 4100055569 · TRANSMITTER · Plant 1000

AReorderCriticalStockout
Material
4100055569
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
74 d · P80 126 d
Unit price
Rp 34.1M (est.)

Recommendation

  • 1.Forecast 0.8 EA/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~74 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 102.4M · order by 01 Oct 2026
Expected arrival ≈ 74 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 16%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 75 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 653.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 5 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PIT-450-23
VD-1906 PRESSURE
A100.04
PX_LIT-657A
LEVEL
B100.03
PX_TIT-1990-56
KC-224A TEMPERATURE
C120.47
PX_PIT-1312C
PRESSURE
C100.04
PY_TIT-632
TEMPERATURE
S130.90

Lead time and procurement

Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026MediumPY_TIT-632Check TIT-632.ok
14 Oct 2025LowPY_TIT-632TIT-632 error
09 Sept 2025LowPX_TIT-1990-56TIT-1990-56 reading frozen
12 May 2025LowPY_TIT-632Install scaffolding at TIT-632
02 May 2025HighPX_TIT-1990-56TIT-1990-56 reading frozen

Recent goods issues

Posting dateQtyOrderOrder type
18 Jul 20261201000013225Corrective