TRANSMITTER,PRESS,SIZE VO777,VITON
Material 4100055618 · TRANSMITTER · Plant 1000
ALong-leadMaintainHealthy
- Material
- 4100055618
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 8 FuncLocs A/B)
- Supplier
- PERMATA INSTRUMEN INTERNASIONAL PT
- Lead time
- 110 d · P80 126 d
- Unit price
- Rp 45.0M
Recommendation
- 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~110 days; expected demand during lead time 0.3.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 8 FuncLoc(s), 5 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
2 / 1
next delivery 24 Mar 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.6%
stockout risk now 0%
Unit price
Rp 45.0M
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 165 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 776.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 8 functional locations
5 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FIT-600-3B PP-287D INLET FLOW | A | 1 | 1 | 0.04 |
| PX_TIT-414C TEMPERATURE | A | 1 | 1 | 0.47 |
| PX_FIT-1125A FLUSHING OIL FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-1115 HE-605 INLET FLOW | B | 1 | 2 | 0.47 |
| PX_FIT-214B FLOW | B | 1 | 0 | 0.04 |
| PX_PIT-427B-28 QUENCH WATER PRESSURE | C | 1 | 1 | 0.04 |
| PX_FIT-1957A FLOW | C | 1 | 0 | 0.04 |
| PX_TIT-117A HE-391 TEMPERATURE | S | 4 | 0 | 0.04 |
Lead time and procurement
Lead time 110 ± 45 days (PO history + category, 1 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 18 Aug 2026 | PR06 Regular replenishment | 1 | Rp 45.0M | 24 Mar 2027 open | 218 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Aug 2026 | Low | PX_FIT-1115 | FIT-1115 error |
| 08 Jun 2025 | Medium | PX_TIT-414C | Leak from packing |
| 20 May 2025 | Low | PX_FIT-600-3B | AR25/tranmsitter low performance |
| 07 May 2025 | Medium | PX_FIT-1115 | PSM25/AR25/tranmsitter low performance |
| 07 May 2025 | Medium | PX_PIT-427B-28 | AR25/tranmsitter low performance |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Apr 2026 | 1 | 201000010635 | Corrective |
| 15 Jan 2026 | 1 | 201000025571 | Corrective |