TRANSMITTER,PRESS,TYPE FO290,SS304

Material 4100056408 · TRANSMITTER · Plant 1000

BLong-leadReduceExcess
Material
4100056408
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
B (2 of 2 FuncLocs A/B)
Supplier
MEGA TEKNIK MAKMUR PT
Lead time
75 d · P80 97 d
Unit price
Rp 53.0M

Recommendation

  • 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~75 days; expected demand during lead time 0.1.
  • 3.A 93.1% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 16 exceeds the level to keep (9) by 7; the level includes the 9 used in the last turnaround.
  • 5.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadLast turnaround used 9Single sourceOpen PO
On hand / on order
16 / 7
next delivery 01 Nov 2026
Today Min / Max
3 / 7
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
93.1%
stockout risk now 0%
Unit price
Rp 53.0M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 134 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (9 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 68.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~37 days.

Installed on 2 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1437-24B
FLOW
B400.04
PX_FIT-627-37A
CL-1319 INLET FLOW
B100.04

Lead time and procurement

Lead time 75 ± 39 days (PO history, 6 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
02 Sept 2026PR06
Regular replenishment
3Rp 51.9M20 Nov 2026
open
79 d
25 Aug 2026PR03
Regular replenishment
4Rp 52.8M01 Nov 2026
open
68 d
07 Sept 2025PR06
Regular replenishment
2Rp 53.4M22 Oct 202545 d
17 Aug 2025PR06
Regular replenishment
3Rp 52.1M17 Sept 202531 d
25 Jul 2025PR03
Regular replenishment
2Rp 55.9M30 Oct 202597 d
29 May 2025PR03
Regular replenishment
2Rp 53.1M06 Oct 2025130 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
20 May 20261201000007134Corrective
18 Dec 20251203000019939Turnaround
28 Nov 20251203000032713Turnaround
26 Nov 20254203000032713Turnaround
26 Nov 20251203000032713Turnaround
25 Nov 20251203000032713Turnaround
24 Nov 20251203000032713Turnaround