TRANSMITTER,PRESS,TYPE FO290,SS304
Material 4100056408 · TRANSMITTER · Plant 1000
BLong-leadReduceExcess
- Material
- 4100056408
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (2 of 2 FuncLocs A/B)
- Supplier
- MEGA TEKNIK MAKMUR PT
- Lead time
- 75 d · P80 97 d
- Unit price
- Rp 53.0M
Recommendation
- 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~75 days; expected demand during lead time 0.1.
- 3.A 93.1% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 16 exceeds the level to keep (9) by 7; the level includes the 9 used in the last turnaround.
- 5.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadLast turnaround used 9Single sourceOpen PO
On hand / on order
16 / 7
next delivery 01 Nov 2026
Today Min / Max
3 / 7
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
93.1%
stockout risk now 0%
Unit price
Rp 53.0M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 134 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 68.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~37 days.
Installed on 2 functional locations
2 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FIT-1437-24B FLOW | B | 4 | 0 | 0.04 |
| PX_FIT-627-37A CL-1319 INLET FLOW | B | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 75 ± 39 days (PO history, 6 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 02 Sept 2026 | PR06 Regular replenishment | 3 | Rp 51.9M | 20 Nov 2026 open | 79 d |
| 25 Aug 2026 | PR03 Regular replenishment | 4 | Rp 52.8M | 01 Nov 2026 open | 68 d |
| 07 Sept 2025 | PR06 Regular replenishment | 2 | Rp 53.4M | 22 Oct 2025 | 45 d |
| 17 Aug 2025 | PR06 Regular replenishment | 3 | Rp 52.1M | 17 Sept 2025 | 31 d |
| 25 Jul 2025 | PR03 Regular replenishment | 2 | Rp 55.9M | 30 Oct 2025 | 97 d |
| 29 May 2025 | PR03 Regular replenishment | 2 | Rp 53.1M | 06 Oct 2025 | 130 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 May 2026 | 1 | 201000007134 | Corrective |
| 18 Dec 2025 | 1 | 203000019939 | Turnaround |
| 28 Nov 2025 | 1 | 203000032713 | Turnaround |
| 26 Nov 2025 | 4 | 203000032713 | Turnaround |
| 26 Nov 2025 | 1 | 203000032713 | Turnaround |
| 25 Nov 2025 | 1 | 203000032713 | Turnaround |
| 24 Nov 2025 | 1 | 203000032713 | Turnaround |