TRANSMITTER,PRESS,MODEL RW974,GRAPHITE

Material 4100056955 · TRANSMITTER · Plant 1000

ALong-leadReduceSlow-moving
Material
4100056955
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
BERKAH ELEKTRIK SENTOSA PT
Lead time
87 d · P80 110 d
Unit price
Rp 38.4M

Recommendation

  • 1.Forecast 0.7 EA/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~87 days; expected demand during lead time 0.2.
  • 3.A 94.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
  • 4.Stock 4 exceeds the level to keep (3) by 1.
  • 5.Long lead time: 80% of deliveries took up to 110 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
94.8%
stockout risk now 0%
Unit price
Rp 38.4M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 243 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 177.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-921B
FLUSHING OIL FLOW
A100.04

Lead time and procurement

Lead time 87 ± 32 days (PO history, 3 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
30 Mar 2026PR03
Regular replenishment
1Rp 40.2M22 Jun 202684 d
18 Jul 2025PR03
Regular replenishment
1Rp 37.6M21 Oct 202595 d
23 Jun 2025PR06
Regular replenishment
2Rp 38.4M21 Oct 2025120 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
31 Jan 20261201000001793Corrective
31 Jan 20262201000001793Corrective