TRANSMITTER,DIFF.PRESS,0~5000MMH2O,HART

Material 4100057194 · TRANSMITTER · Plant 1000

ALong-leadMonitorStockout
Material
4100057194
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (22 of 62 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
95 d · P80 143 d
Unit price
Rp 39.5M

Recommendation

  • 1.Forecast 15 EA/year: 15 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~95 days; expected demand during lead time 3.9.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 15.
  • 4.Long lead time: 80% of deliveries took up to 143 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 62 FuncLoc(s), 22 of them criticality A/B.
  • 6.ML early warning: 92% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceAbnormal consumptionOpen POSame description as 5 other material numbers
On hand / on order
0 / 27
next delivery 25 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 9
Rec. Max
15
order qty 3
Service level
99.8%
stockout risk now 0%
Unit price
Rp 39.5M
PO history
ML early warning: 92% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 48 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 7 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Lumpy · 17 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 62 functional locations

22 with criticality A/B · 76 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_DPT-956-2A
DIFF. PRESSURE
A141.35
PX_PIT-1063-22B
PRESSURE
A240.90
PX_FIT-1974B
FLOW
A120.47
PY_PIT-578A
CL-1481 PRESSURE
A120.47
PX_FIT-921B
FLUSHING OIL FLOW
A400.04
PX_PIT-1100C
PRESSURE
A100.04
PX_PIT-1657
PRESSURE
A100.04
PX_PIT-1707A
PRESSURE
A100.04
PX_PIT-644
REFLUX PRESSURE
A100.04
PX_TIT-199
CL-658 TEMPERATURE
A100.04
PX_TIT-829-55
VD-609 TEMPERATURE
A100.04
PX_LIT-999A-15A
LEVEL
B110.46

Lead time and procurement

Lead time 95 ± 57 days (PO history, 13 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
12 Sept 2026PR06
Regular replenishment
14Rp 38.6M25 Oct 2026
open
43 d
30 Aug 2026PR05
Project / turnaround
7Rp 40.0M30 Jan 2027
open
153 d
16 Jul 2026PR06
Regular replenishment
7Rp 38.7M07 Sept 202653 d
02 Jul 2026PR06
Regular replenishment
9Rp 39.2M14 Sept 202674 d
12 Jun 2026PR06
Regular replenishment
6Rp 39.5M31 Aug 202680 d
27 Apr 2026PR03
Regular replenishment
6Rp 40.3M10 Nov 2026
open
197 d
10 Apr 2026PR05
Project / turnaround
5Rp 40.4M15 Aug 2026127 d
24 Nov 2025PR06
Regular replenishment
7Rp 39.7M12 Feb 202680 d
06 Nov 2025PR03
Regular replenishment
11Rp 41.1M12 Jan 202667 d
16 Oct 2025PR06
Regular replenishment
15Rp 38.3M29 Nov 202544 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Aug 2026LowPX_DPT-956-2ADPT-956-2A abnormal indication
08 Aug 2026HighPX_FIT-140FIT-140 error
17 Jun 2026MediumPX_DPT-956-2ALeak from packing
06 Jun 2026LowPY_PIT-578AReplace lamp as per PM finding
20 May 2026MediumPX_PIT-578AAR25/tranmsitter low performance
14 Apr 2026LowPX_PIT-1063-22BPainting PIT-1063-22B
02 Apr 2026MediumPX_PIT-1063-22BAR25/tranmsitter low performance
29 Mar 2026EmergencyPX_FIT-686A[MSI-B-26-YLM-221] Permanent repair
06 Mar 2026MediumPX_FIT-1974BCheck FIT-1974B.ok
24 Feb 2026MediumPX_PIT-578AInstall scaffolding at PIT-578A

Recent goods issues

Posting dateQtyOrderOrder type
14 Aug 20261201000011252Corrective
20 Jun 20262201000020155Corrective
19 Jun 20263201000024332Corrective
03 Jun 20261201000012166Corrective
07 May 20261204000003804Preventive
12 Mar 20261201000023690Corrective
31 Jan 20261201000001793Corrective
13 Jan 20261201000039896Corrective
15 Dec 20253201000036707Corrective
02 Dec 20251201000008858Corrective
01 Dec 20251201000008858Corrective
17 Oct 20252201000009960Corrective
09 Aug 20251201000004846Corrective
15 Jul 20251201000019096Corrective
03 Jul 20259201000031242Corrective
Sparely