TRANSMITTER,DIFF.PRESS,0~500MMH2O,HART

Material 4100057214 · TRANSMITTER · Plant 1000

ALong-leadMaintainHealthy
Material
4100057214
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (14 of 32 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
76 d · P80 101 d
Unit price
Rp 42.9M

Recommendation

  • 1.Forecast 5.8 EA/year: 5.8 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~76 days; expected demand during lead time 1.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 8.
  • 4.Long lead time: 80% of deliveries took up to 101 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 32 FuncLoc(s), 14 of them criticality A/B.
  • 6.ML early warning: 37% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceOpen POSame description as 6 other material numbers
On hand / on order
8 / 3
next delivery 22 Jan 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
8
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 42.9M
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 11 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 9 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 32 functional locations

14 with criticality A/B · 42 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1489
PP-1194 INLET FLOW
A120.47
PX_DPT-1291-5B
VD-185 DP
A400.06
PX_FIT-803-18A
LEAN AMINE FLOW
A100.04
PX_LIT-232C-57B
PP-1022B LEVEL
A100.03
PX_PIT-1377
COOLING WATER PRESSURE
A100.04
PX_TIT-614D
TEMPERATURE
A100.04
PX_PIT-1008
CONDENSATE PRESSURE
B120.47
PX_FIT-1740
FLOW
B200.04
PX_FIT-1745-46B
LUBE OIL FLOW
B100.04
PX_FIT-1757
PP-1891B INLET FLOW
B100.04
PX_FIT-558
HE-1078B INLET FLOW
B100.04
PX_PIT-1096-3
PRESSURE
B100.04

Lead time and procurement

Lead time 76 ± 48 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
22 Aug 2026PR06
Regular replenishment
3Rp 42.4M22 Jan 2027
open
153 d
18 Mar 2026PR03
Regular replenishment
6Rp 40.6M30 Apr 202643 d
01 Nov 2025PR06
Regular replenishment
2Rp 44.4M21 Dec 202550 d
02 Oct 2025PR10
Other
3Rp 43.5M07 Dec 202566 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jun 2026EmergencyPX_FIT-1489Replace lamp as per PM finding
11 Nov 2025MediumPX_TIT-701C-7Leak from packing
08 Nov 2025MediumPX_PIT-1008Replace lamp as per PM finding
28 May 2025HighPX_PIT-1008Check PIT-1008.ok
21 May 2025HighPX_FIT-547AReplace lamp as per PM finding
20 May 2025LowPX_FIT-214-54AFIT-214-54A abnormal indication
19 May 2025LowPX_FIT-1522-39BAR25/tranmsitter low performance
16 May 2025MediumPX_TIT-701C-7[MSI-B-25-XFH-308/M] Replace line
13 May 2025MediumPX_FIT-1489[MSI-B-25-UTF-163] Permanent repair
11 May 2025LowPX_LIT-1775-50Check LIT-1775-50.ok

Recent goods issues

Posting dateQtyOrderOrder type
20 Sept 20261201000037306Corrective
24 Jul 20261203000004330Turnaround
09 Jul 20261201000019202Corrective
27 Feb 20261201000024281Corrective
31 Jan 20261201000001515Corrective
18 Jan 20261201000037627Corrective
28 Oct 20251201000030030Corrective
27 Oct 20251201000010024Corrective
03 Aug 20251201000005097Corrective
17 May 20252201000014247Corrective