TRANSMITTER,DIFF.PRESS,0~10000MMH2O,FF

Material 4100057232 · TRANSMITTER · Plant 1000

ALong-leadReduceExcess
Material
4100057232
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (6 of 22 FuncLocs A/B)
Supplier
GUNUNG PERKASA NUSANTARA PT
Lead time
95 d · P80 124 d
Unit price
Rp 43.0M

Recommendation

  • 1.Forecast 3.5 EA/year: 3.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.9.
  • 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
  • 4.Stock 8 exceeds the level to keep (7) by 1.
  • 5.Long lead time: 80% of deliveries took up to 124 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 22 FuncLoc(s), 6 of them criticality A/B.
Long-leadSingle sourceSame description as 9 other material numbers
On hand / on order
8 / 0
no open PO
Today Min / Max
4 / 6
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
7
order qty 2
Service level
99.6%
stockout risk now 0%
Unit price
Rp 43.0M
PO history
ML early warning: 21% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 9 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 22 functional locations

6 with criticality A/B · 22 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1842
FLOW
A100.04
PX_PIT-1100C
PRESSURE
A100.04
PX_TIT-302A-59A
TEMPERATURE
A100.04
PX_DPT-1335A
PP-1914D DP
B100.06
PX_LIT-1273D
KC-536A LEVEL
B100.03
PX_PIT-1770
RICH AMINE PRESSURE
B100.04
PX_DPT-695-29B
HE-1422A DP
C100.06
PX_DPT-703-13
PP-362B DP
C100.06
PX_FIT-1227
FUEL OIL FLOW
C100.04
PX_LIT-1726
PP-387 LEVEL
C100.03
PX_LIT-860
PP-882A LEVEL
C100.03
PX_TIT-1088
TEMPERATURE
C100.04

Lead time and procurement

Lead time 95 ± 37 days (PO history, 4 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
24 Apr 2026PR05
Project / turnaround
3Rp 42.4M29 Sept 2026158 d
24 Apr 2026PR03
Regular replenishment
2Rp 43.5M02 Aug 2026100 d
06 Apr 2026PR03
Regular replenishment
1Rp 41.9M17 Jul 2026102 d
13 Jun 2025PR03
Regular replenishment
2Rp 44.3M07 Sept 202586 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Mar 2026EmergencyPX_FIT-686A[MSI-B-26-YLM-221] Permanent repair
24 May 2025MediumPX_FIT-686AFIT-686A error

Recent goods issues

Posting dateQtyOrderOrder type
22 Sept 20263201000006563Corrective
29 Dec 20251201000035558Corrective
28 Dec 20251201000035558Corrective
15 Dec 20251201000036707Corrective