TRANSMITTER,DIFF.PRESS,0~10000MMH2O,FF
Material 4100057232 · TRANSMITTER · Plant 1000
ALong-leadReduceExcess
- Material
- 4100057232
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 22 FuncLocs A/B)
- Supplier
- GUNUNG PERKASA NUSANTARA PT
- Lead time
- 95 d · P80 124 d
- Unit price
- Rp 43.0M
Recommendation
- 1.Forecast 3.5 EA/year: 3.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~95 days; expected demand during lead time 0.9.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
- 4.Stock 8 exceeds the level to keep (7) by 1.
- 5.Long lead time: 80% of deliveries took up to 124 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 22 FuncLoc(s), 6 of them criticality A/B.
Long-leadSingle sourceSame description as 9 other material numbers
On hand / on order
8 / 0
no open PO
Today Min / Max
4 / 6
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
7
order qty 2
Service level
99.6%
stockout risk now 0%
Unit price
Rp 43.0M
PO history
ML early warning: 21% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 9 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 22 functional locations
6 with criticality A/B · 22 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FIT-1842 FLOW | A | 1 | 0 | 0.04 |
| PX_PIT-1100C PRESSURE | A | 1 | 0 | 0.04 |
| PX_TIT-302A-59A TEMPERATURE | A | 1 | 0 | 0.04 |
| PX_DPT-1335A PP-1914D DP | B | 1 | 0 | 0.06 |
| PX_LIT-1273D KC-536A LEVEL | B | 1 | 0 | 0.03 |
| PX_PIT-1770 RICH AMINE PRESSURE | B | 1 | 0 | 0.04 |
| PX_DPT-695-29B HE-1422A DP | C | 1 | 0 | 0.06 |
| PX_DPT-703-13 PP-362B DP | C | 1 | 0 | 0.06 |
| PX_FIT-1227 FUEL OIL FLOW | C | 1 | 0 | 0.04 |
| PX_LIT-1726 PP-387 LEVEL | C | 1 | 0 | 0.03 |
| PX_LIT-860 PP-882A LEVEL | C | 1 | 0 | 0.03 |
| PX_TIT-1088 TEMPERATURE | C | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 95 ± 37 days (PO history, 4 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 24 Apr 2026 | PR05 Project / turnaround | 3 | Rp 42.4M | 29 Sept 2026 | 158 d |
| 24 Apr 2026 | PR03 Regular replenishment | 2 | Rp 43.5M | 02 Aug 2026 | 100 d |
| 06 Apr 2026 | PR03 Regular replenishment | 1 | Rp 41.9M | 17 Jul 2026 | 102 d |
| 13 Jun 2025 | PR03 Regular replenishment | 2 | Rp 44.3M | 07 Sept 2025 | 86 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Mar 2026 | Emergency | PX_FIT-686A | [MSI-B-26-YLM-221] Permanent repair |
| 24 May 2025 | Medium | PX_FIT-686A | FIT-686A error |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Sept 2026 | 3 | 201000006563 | Corrective |
| 29 Dec 2025 | 1 | 201000035558 | Corrective |
| 28 Dec 2025 | 1 | 201000035558 | Corrective |
| 15 Dec 2025 | 1 | 201000036707 | Corrective |