TRANSMITTER,DIFF.PRESS,0~5000MMH2O,FF

Material 4100057273 · TRANSMITTER · Plant 1000

AReduceSlow-moving
Material
4100057273
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (8 of 13 FuncLocs A/B)
Supplier
No PO history
Lead time
74 d · P80 126 d
Unit price
Rp 34.1M (est.)

Recommendation

  • 1.Forecast 1.4 EA/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~74 days; expected demand during lead time 0.3.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 4 exceeds the level to keep (3) by 1.
  • 5.Installed on 13 FuncLoc(s), 8 of them criticality A/B.
Price estimatedLead time estimatedSame description as 7 other material numbers
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 26% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 266 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 13 functional locations

8 with criticality A/B · 13 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TIT-1403D
PP-1309A TEMPERATURE
A130.90
PX_FIT-600-3B
PP-287D INLET FLOW
A110.04
PX_PIT-1963B-50
HE-1756B PRESSURE
A110.47
PX_FIT-181
CHARGE GAS FLOW
A100.04
PX_FIT-774B
WASH WATER FLOW
A100.04
PX_PIT-1298-23A
PRESSURE
A100.04
PX_FIT-383A
FLOW
B120.90
PY_PIT-123C
COOLING WATER PRESSURE
B100.04
PX_LIT-1731
HE-1959 LEVEL
C100.03
PX_LIT-888-19B
LEVEL
C100.03
PX_TIT-1562
TEMPERATURE
S120.47
PX_FIT-1653
INHIBITOR FLOW
S110.47

Lead time and procurement

Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Sept 2026LowPX_TIT-1403DRepair insulation TIT-1403D
09 Sept 2026HighPX_TIT-1562TIT-1562 error
14 Jul 2026MediumPX_FIT-383AFIT-383A reading frozen
07 Apr 2026LowPX_TIT-1403DTIT-1403D abnormal indication
26 Jul 2025MediumPX_FIT-383AAR25/tranmsitter low performance
08 Jul 2025MediumPX_PIT-1963B-50PIT-1963B-50 reading frozen
13 Jun 2025LowPX_FIT-1653Repair insulation FIT-1653
20 May 2025LowPX_FIT-600-3BAR25/tranmsitter low performance
17 May 2025MediumPX_TIT-1403DInstall scaffolding at TIT-1403D
05 May 2025MediumPX_TIT-1562TIT-1562 error

Recent goods issues

Posting dateQtyOrderOrder type
08 Jan 20261201000031760Corrective
25 Oct 20251201000020545Corrective
15 Aug 20251201000024285Corrective