TRANSMITTER,DIFF.PRESS,0~5000MMH2O,FF
Material 4100057273 · TRANSMITTER · Plant 1000
AReduceSlow-moving
- Material
- 4100057273
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (8 of 13 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 74 d · P80 126 d
- Unit price
- Rp 34.1M (est.)
Recommendation
- 1.Forecast 1.4 EA/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~74 days; expected demand during lead time 0.3.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Stock 4 exceeds the level to keep (3) by 1.
- 5.Installed on 13 FuncLoc(s), 8 of them criticality A/B.
Price estimatedLead time estimatedSame description as 7 other material numbers
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 26% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 266 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 13 functional locations
8 with criticality A/B · 13 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TIT-1403D PP-1309A TEMPERATURE | A | 1 | 3 | 0.90 |
| PX_FIT-600-3B PP-287D INLET FLOW | A | 1 | 1 | 0.04 |
| PX_PIT-1963B-50 HE-1756B PRESSURE | A | 1 | 1 | 0.47 |
| PX_FIT-181 CHARGE GAS FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-774B WASH WATER FLOW | A | 1 | 0 | 0.04 |
| PX_PIT-1298-23A PRESSURE | A | 1 | 0 | 0.04 |
| PX_FIT-383A FLOW | B | 1 | 2 | 0.90 |
| PY_PIT-123C COOLING WATER PRESSURE | B | 1 | 0 | 0.04 |
| PX_LIT-1731 HE-1959 LEVEL | C | 1 | 0 | 0.03 |
| PX_LIT-888-19B LEVEL | C | 1 | 0 | 0.03 |
| PX_TIT-1562 TEMPERATURE | S | 1 | 2 | 0.47 |
| PX_FIT-1653 INHIBITOR FLOW | S | 1 | 1 | 0.47 |
Lead time and procurement
Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Sept 2026 | Low | PX_TIT-1403D | Repair insulation TIT-1403D |
| 09 Sept 2026 | High | PX_TIT-1562 | TIT-1562 error |
| 14 Jul 2026 | Medium | PX_FIT-383A | FIT-383A reading frozen |
| 07 Apr 2026 | Low | PX_TIT-1403D | TIT-1403D abnormal indication |
| 26 Jul 2025 | Medium | PX_FIT-383A | AR25/tranmsitter low performance |
| 08 Jul 2025 | Medium | PX_PIT-1963B-50 | PIT-1963B-50 reading frozen |
| 13 Jun 2025 | Low | PX_FIT-1653 | Repair insulation FIT-1653 |
| 20 May 2025 | Low | PX_FIT-600-3B | AR25/tranmsitter low performance |
| 17 May 2025 | Medium | PX_TIT-1403D | Install scaffolding at TIT-1403D |
| 05 May 2025 | Medium | PX_TIT-1562 | TIT-1562 error |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Jan 2026 | 1 | 201000031760 | Corrective |
| 25 Oct 2025 | 1 | 201000020545 | Corrective |
| 15 Aug 2025 | 1 | 201000024285 | Corrective |