TRANSMITTER,DIFF.PRESS,0~2500MMH2O,HART
Material 4100057333 · TRANSMITTER · Plant 1000
ALong-leadTransferCriticalStockout
- Material
- 4100057333
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- PERMATA INSTRUMEN INTERNASIONAL PT
- Lead time
- 81 d · P80 126 d
- Unit price
- Rp 88.4M
Recommendation
- 1.Forecast 1.8 EA/year: 1.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~81 days; expected demand during lead time 0.4.
- 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.On hand 0 + on order 2 is at or below the reorder point: 1 needed.
- 5.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
- 7.Identical part 4100058397 holds spare stock: transfer 1 EA instead of buying — no purchase needed.
Long-leadConvert to Stock ItemSingle sourceOpen POSame description as 2 other material numbers
On hand / on order
0 / 2
next delivery 26 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.2%
stockout risk now 1%
Unit price
Rp 88.4M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 90 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 7 functional locations
4 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_LIT-385 HE-1671A LEVEL | A | 1 | 2 | 0.46 |
| PX_LIT-722 HE-1660A LEVEL | A | 1 | 1 | 0.03 |
| PX_FIT-774B WASH WATER FLOW | A | 2 | 0 | 0.04 |
| PX_PIT-564C PRESSURE | B | 1 | 0 | 0.04 |
| PX_DPT-724 HE-462C DP | C | 1 | 0 | 0.06 |
| PX_PIT-1689A-21A PRESSURE | C | 1 | 0 | 0.04 |
| PX_TIT-826A HE-1900C TEMPERATURE | C | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 81 ± 45 days (PO history + category, 2 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Sept 2026 | PR06 Regular replenishment | 2 | Rp 88.6M | 26 Dec 2026 open | 108 d |
| 09 Mar 2026 | PR10 Other | 1 | Rp 88.2M | 24 May 2026 | 76 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 01 Nov 2025 | High | PX_LIT-385 | Check LIT-385.ok |
| 29 May 2025 | Medium | PX_LIT-722 | AR25/tranmsitter low performance |
| 23 May 2025 | Medium | PX_LIT-385 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Jul 2026 | 1 | 201000009511 | Corrective |
| 18 Jun 2026 | 1 | 201000018305 | Corrective |
| 06 Dec 2025 | 1 | 205000030097 | Other maintenance |