TRANSMITTER,DIFF.PRESS,0~10000MMH2O,HART

Material 4100057598 · TRANSMITTER · Plant 1000

CReduceSlow-moving
Material
4100057598
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
125 d · P80 193 d
Unit price
Rp 64.7M

Recommendation

  • 1.Forecast 1.4 EA/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~125 days; expected demand during lead time 0.5.
  • 3.A 69.0% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Stock 3 exceeds the level to keep (2) by 1.
Single sourceOpen POSame description as 8 other material numbers
On hand / on order
3 / 3
next delivery 19 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
69.0%
stockout risk now 0%
Unit price
Rp 64.7M
PO history
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 238 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 17.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~37 days.

Installed on 2 functional locations

0 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-728
WASH WATER FLOW
C340.47
PX_TIT-1553
PP-744B TEMPERATURE
C110.04

Lead time and procurement

Lead time 125 ± 59 days (PO history, 4 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR01
Import / long-lead
2Rp 66.3M10 Jun 2027
open
267 d
16 Jul 2026PR03
Regular replenishment
1Rp 64.3M19 Nov 2026
open
126 d
05 Mar 2026PR03
Regular replenishment
2Rp 62.8M27 Jun 2026114 d
25 Nov 2025PR06
Regular replenishment
2Rp 65.2M17 Apr 2026143 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Sept 2026MediumPX_FIT-728Leak from packing
06 Aug 2026MediumPX_FIT-728Install scaffolding at FIT-728
24 Dec 2025LowPX_FIT-728Install scaffolding at FIT-728
14 Jun 2025MediumPX_TIT-1553Install scaffolding at TIT-1553
08 May 2025MediumPX_FIT-728FIT-728 reading frozen

Recent goods issues

Posting dateQtyOrderOrder type
05 Feb 20261201000030018Corrective
19 Sept 20251201000025528Corrective
25 May 20252201000007741Corrective
24 May 20251201000007741Corrective