TRANSMITTER,DIFF.PRESS,0~5000MMH2O,FF

Material 4100057903 · TRANSMITTER · Plant 1000

BLong-leadMonitorSlow-moving
Material
4100057903
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
53 d · P80 126 d
Unit price
Rp 42.8M

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~53 days; expected demand during lead time 0.0.
  • 3.A 97.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceSame description as 7 other material numbers
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
97.8%
stockout risk now 0%
Unit price
Rp 42.8M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 348 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 30.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~37 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_LIT-978-17
LEVEL
B110.03

Lead time and procurement

Lead time 53 ± 45 days (PO history + category, 2 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
18 Jul 2026PR03
Regular replenishment
2Rp 42.3M19 Aug 202632 d
07 Feb 2026PR06
Regular replenishment
2Rp 43.2M18 Feb 202611 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
31 May 2025MediumPY_LIT-978-17PSM25/AR25/tranmsitter low performance

Recent goods issues

Posting dateQtyOrderOrder type
18 Oct 20251201000034273Corrective