TRANSMITTER,DIFF.PRESS,0~5000MMH2O,FF
Material 4100058010 · TRANSMITTER · Plant 1000
BTransferCriticalStockout
- Material
- 4100058010
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 74 d · P80 126 d
- Unit price
- Rp 34.1M (est.)
Recommendation
- 1.Forecast 2.8 EA/year: 2.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~74 days; expected demand during lead time 0.6.
- 3.A 99.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 4.On hand 0 + on order 0 is at or below the reorder point: 5 needed.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
- 6.Identical part 4100058628, 4100057273, 4100058579 holds spare stock: transfer 5 EA instead of buying — no purchase needed.
Convert to Stock ItemPrice estimatedLead time estimatedSame description as 7 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.0%
stockout risk now 35%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 417.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~37 days.
Installed on 3 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_DPT-1916A DIFF. PRESSURE | B | 1 | 4 | 1.35 |
| PX_TIT-1681B TEMPERATURE | C | 1 | 2 | 0.47 |
| PX_PIT-1033-1 HE-149A PRESSURE | C | 3 | 1 | 0.04 |
Lead time and procurement
Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 11 Sept 2026 | Medium | PX_TIT-1681B | Painting TIT-1681B |
| 31 Aug 2026 | Medium | PX_DPT-1916A | Check DPT-1916A.ok |
| 29 Mar 2026 | Medium | PX_DPT-1916A | Leak from packing |
| 08 Sept 2025 | Low | PX_DPT-1916A | DPT-1916A error |
| 08 Aug 2025 | Medium | PX_TIT-1681B | AR25/tranmsitter low performance |
| 23 May 2025 | Low | PX_DPT-1916A | Repair insulation DPT-1916A |
| 12 May 2025 | Medium | PX_PIT-1033-1 | PIT-1033-1 reading frozen |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000029668 | Corrective |
| 18 Feb 2026 | 1 | 201000034128 | Corrective |
| 17 Feb 2026 | 2 | 201000034128 | Corrective |