TRANSMITTER,DIFF.PRESS,0~500MMH2O,FF

Material 4100058024 · TRANSMITTER · Plant 1000

AReduceSlow-moving
Material
4100058024
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
PERMATA INSTRUMEN INTERNASIONAL PT
Lead time
65 d · P80 73 d
Unit price
Rp 24.8M

Recommendation

  • 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~65 days; expected demand during lead time 0.1.
  • 3.A 97.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Stock 70 exceeds the level to keep (2) by 68.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Single sourceSame description as 9 other material numbers
On hand / on order
70 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
97.5%
stockout risk now 0%
Unit price
Rp 24.8M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 423 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 111.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-303
BFW FLOW
A100.04
PY_PIT-1586-16B
PROPYLENE PRESSURE
A100.04
PX_TIT-1570B-57B
HE-1855B TEMPERATURE
S100.04

Lead time and procurement

Lead time 65 ± 39 days (PO history, 3 PO lines) · on-time 47%

PR dateTypeQtyUnit priceDeliveryLead time
03 Mar 2026PR03
Regular replenishment
2Rp 25.7M04 Jun 202693 d
20 Feb 2026PR03
Regular replenishment
2Rp 24.5M03 Apr 202642 d
06 Oct 2025PR06
Regular replenishment
1Rp 24.8M05 Nov 202530 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
04 Aug 20252204000023047Preventive