TRANSMITTER,DIFF.PRESS,0~500MMH2O,FF

Material 4100058151 · TRANSMITTER · Plant 1000

ALong-leadMonitorSlow-moving
Material
4100058151
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
108 d · P80 162 d
Unit price
Rp 82.3M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~108 days; expected demand during lead time 0.1.
  • 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 162 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen POSame description as 9 other material numbers
On hand / on order
1 / 1
next delivery 15 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.4%
stockout risk now 0%
Unit price
Rp 82.3M
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 217 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 299.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PIT-352
HE-1144C PRESSURE
A110.47
PX_PIT-1353C
CONDENSATE PRESSURE
S100.04

Lead time and procurement

Lead time 108 ± 42 days (PO history, 3 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
12 May 2026PR01
Import / long-lead
1Rp 81.8M15 Nov 2026
open
187 d
20 Aug 2025PR06
Regular replenishment
2Rp 84.2M11 Dec 2025113 d
18 Jun 2025PR06
Regular replenishment
1Rp 82.3M20 Oct 2025124 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jul 2025HighPX_PIT-352AR25/tranmsitter low performance

Recent goods issues

Posting dateQtyOrderOrder type
26 Feb 20261201000000733Corrective