TRANSMITTER,TEMP,MODEL GR348,NBR
Material 4100058864 · TRANSMITTER · Plant 1000
AReorderCriticalStockout
- Material
- 4100058864
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (26 of 64 FuncLocs A/B)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 55 d · P80 65 d
- Unit price
- Rp 28.2M
Recommendation
- 1.Forecast 14 EA/year: 14 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~55 days; expected demand during lead time 2.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 11.
- 4.On hand 0 + on order 6 is at or below the reorder point: order 5 now.
- 5.Installed on 64 FuncLoc(s), 26 of them criticality A/B.
- 6.ML early warning: 91% probability of demand in the next 90 days.
Proposed purchase requisition
5 EA
Rp 141.0M · order by 01 Oct 2026
Expected arrival ≈ 55 days
ML early warningSingle sourceOpen PO
On hand / on order
0 / 6
next delivery 29 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
11
order qty 3
Service level
99.9%
stockout risk now 1%
Unit price
Rp 28.2M
PO history
ML early warning: 91% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 10 days ago, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 15 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 64 functional locations
26 with criticality A/B · 81 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_FIT-1105 QUENCH WATER FLOW | A | 1 | 4 | 0.90 |
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_FIT-194 FLOW | A | 3 | 1 | 0.47 |
| PX_FIT-1560A SLOP OIL FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-1939-27B QUENCH OIL FLOW | A | 1 | 0 | 0.04 |
| PX_FIT-721-9B SPENT CAUSTIC FLOW | A | 1 | 0 | 0.04 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_LIT-1813 PP-992B LEVEL | A | 1 | 0 | 0.03 |
Lead time and procurement
Lead time 55 ± 25 days (PO history, 10 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Sept 2026 | PR03 Regular replenishment | 6 | Rp 29.0M | 29 Oct 2026 open | 39 d |
| 19 May 2026 | PR03 Regular replenishment | 6 | Rp 27.4M | 12 Jun 2026 | 24 d |
| 06 Apr 2026 | PR01 Import / long-lead | 4 | Rp 27.7M | 28 Jun 2026 | 83 d |
| 27 Mar 2026 | PR04 Regular (other) | 4 | Rp 29.4M | 09 Jun 2026 | 74 d |
| 06 Mar 2026 | PR03 Regular replenishment | 6 | Rp 28.7M | 08 May 2026 | 63 d |
| 04 Mar 2026 | PR06 Regular replenishment | 8 | Rp 28.1M | 01 May 2026 | 58 d |
| 10 Nov 2025 | PR03 Regular replenishment | 6 | Rp 27.7M | 17 Dec 2025 | 37 d |
| 07 Oct 2025 | PR03 Regular replenishment | 8 | Rp 28.8M | 14 Nov 2025 | 38 d |
| 29 Aug 2025 | PR06 Regular replenishment | 7 | Rp 28.3M | 09 Oct 2025 | 41 d |
| 26 Jul 2025 | PR06 Regular replenishment | 8 | Rp 28.1M | 03 Sept 2025 | 39 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_PIT-758 | Install scaffolding at PIT-758 |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 11 Sept 2026 | Medium | PX_TIT-1681B | Painting TIT-1681B |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 16 Aug 2026 | Low | PX_TIT-356A | Install scaffolding at TIT-356A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Sept 2026 | 1 | 201000004785 | Corrective |
| 11 Sept 2026 | 1 | 201000020312 | Corrective |
| 16 Jul 2026 | 1 | 201000007763 | Corrective |
| 15 Jul 2026 | 1 | 201000007763 | Corrective |
| 25 May 2026 | 1 | 201000037573 | Corrective |
| 20 May 2026 | 1 | 201000007134 | Corrective |
| 19 Apr 2026 | 1 | 201000026708 | Corrective |
| 20 Jan 2026 | 1 | 206000015919 | Other maintenance |
| 19 Jan 2026 | 2 | 206000015919 | Other maintenance |
| 13 Jan 2026 | 1 | 201000039896 | Corrective |
| 07 Jan 2026 | 1 | 201000023460 | Corrective |
| 29 Dec 2025 | 1 | 201000025173 | Corrective |
| 08 Dec 2025 | 1 | 201000017361 | Corrective |
| 16 Aug 2025 | 1 | 201000029011 | Corrective |
| 29 Jul 2025 | 1 | 201000002449 | Corrective |