TRANSMITTER,TEMP,SIZE XH198,INCOLOY
Material 4100058923 · TRANSMITTER · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100058923
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (11 of 19 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 86 d · P80 139 d
- Unit price
- Rp 8.8M
Recommendation
- 1.Forecast 7.4 EA/year: 7.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~86 days; expected demand during lead time 1.7.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 12.
- 4.On hand 2 + on order 2 is at or below the reorder point: order 8 now.
- 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 19 FuncLoc(s), 11 of them criticality A/B.
Proposed purchase requisition
8 EA
Rp 70.4M · order by 01 Oct 2026
Expected arrival ≈ 86 days
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 10 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
12
order qty 4
Service level
99.9%
stockout risk now 11%
Unit price
Rp 8.8M
PO history
ML early warning: 25% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 272 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 19 functional locations
11 with criticality A/B · 21 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-460B TURBINE FOR KC-460B | A | 2 | 2 | 1.96 |
| PX_FIT-930A-26B FLOW | A | 1 | 1 | 0.47 |
| PX_PIT-1343A PRESSURE | A | 1 | 1 | 0.04 |
| PX_FIT-1992A-33B PP-1751A INLET FLOW | A | 1 | 0 | 0.04 |
| PX_LIT-799C LEVEL | A | 1 | 0 | 0.03 |
| PX_PIT-1311B PRESSURE | A | 1 | 0 | 0.04 |
| PX_TIT-256A TEMPERATURE | B | 1 | 1 | 0.04 |
| PX_FIT-1676A METHANOL FLOW | B | 1 | 0 | 0.04 |
| PX_LIT-1560 KC-372D LEVEL | B | 1 | 0 | 0.03 |
| PX_FIT-235D-57A HE-955C INLET FLOW | C | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 86 ± 60 days (PO history, 3 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 25 Aug 2026 | PR04 Regular (other) | 2 | Rp 8.9M | 10 Nov 2026 open | 77 d |
| 26 Oct 2025 | PR05 Project / turnaround | 2 | Rp 8.7M | 24 Apr 2026 | 180 d |
| 10 May 2025 | PR06 Regular replenishment | 1 | Rp 8.8M | 13 Jun 2025 | 34 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
| 19 Apr 2026 | Low | PX_KT-447 | Follow up after steam upset KT-447 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 Jan 2026 | 2 | 201000013250 | Corrective |
| 15 Nov 2025 | 1 | 201000021456 | Corrective |