TRANSMITTER,TEMP,MODEL ZD117,CS

Material 4100059054 · TRANSMITTER · Plant 1000

ALong-leadMonitorStockout
Material
4100059054
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (4 of 6 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
74 d · P80 97 d
Unit price
Rp 26.2M

Recommendation

  • 1.Forecast 0.5 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~74 days; expected demand during lead time 0.1.
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
  • 6.ML early warning: 46% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 4
next delivery 01 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.5%
stockout risk now 0%
Unit price
Rp 26.2M
PO history
ML early warning: 46% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 281 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 401.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LIT-243
LEVEL
A100.03
PX_PIT-661A-18
FLUSHING OIL PRESSURE
B100.04
PX_TIT-1414A
TEMPERATURE
B100.04
PX_TIT-734-33A
CL-1019 TEMPERATURE
B100.04
PX_LIT-1188
HE-192B LEVEL
C110.03
PX_DPT-1725
DIFF. PRESSURE
S100.06

Lead time and procurement

Lead time 74 ± 55 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
13 Aug 2026PR03
Regular replenishment
2Rp 24.7M01 Oct 2026
open
49 d
28 May 2026PR01
Import / long-lead
2Rp 26.6M13 Nov 2026
open
169 d
13 Jan 2026PR06
Regular replenishment
1Rp 26.6M28 Feb 202646 d
23 Sept 2025PR06
Regular replenishment
1Rp 25.8M26 Oct 202533 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 May 2025MediumPX_LIT-1188Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
24 Dec 20251201000029199Corrective
05 Sept 20251201000001030Corrective