TRANSMITTER,TEMP,SIZE GU679,NBR

Material 4100059165 · TRANSMITTER · Plant 1000

ALong-leadReduceSlow-moving
Material
4100059165
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 7 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
95 d · P80 133 d
Unit price
Rp 17.2M

Recommendation

  • 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.6.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.Stock 130 exceeds the level to keep (5) by 125.
  • 5.Long lead time: 80% of deliveries took up to 133 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 7 FuncLoc(s), 3 of them criticality A/B.
  • 7.ML early warning: 33% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceOpen PO
On hand / on order
130 / 2
next delivery 05 Apr 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.7%
stockout risk now 0%
Unit price
Rp 17.2M
PO history
ML early warning: 33% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 302 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 7 functional locations

3 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_DPT-956-2A
DIFF. PRESSURE
A141.35
PX_PIT-1063-22B
PRESSURE
A140.90
PX_PIT-1324
PRESSURE
B100.04
PX_TIT-743A
HE-1441D TEMPERATURE
C400.04
PX_KT-778A
TURBINE FOR KC-778A
S101.10
PX_LIT-598A
LEVEL
S100.03
PX_PIT-1353C
CONDENSATE PRESSURE
S100.04

Lead time and procurement

Lead time 95 ± 75 days (PO history, 5 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
06 Jul 2026PR01
Import / long-lead
2Rp 17.6M05 Apr 2027
open
273 d
20 Apr 2026PR06
Regular replenishment
2Rp 16.6M17 Jun 202658 d
12 Jul 2025PR06
Regular replenishment
1Rp 17.2M18 Oct 202598 d
09 Jun 2025PR06
Regular replenishment
2Rp 17.6M28 Jul 202549 d
16 May 2025PR03
Regular replenishment
1Rp 16.7M18 Jul 202563 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Aug 2026LowPX_DPT-956-2ADPT-956-2A abnormal indication
17 Jun 2026MediumPX_DPT-956-2ALeak from packing
14 Apr 2026LowPX_PIT-1063-22BPainting PIT-1063-22B
02 Apr 2026MediumPX_PIT-1063-22BAR25/tranmsitter low performance
11 Oct 2025LowPX_PIT-1063-22BAR25/tranmsitter low performance
17 Aug 2025LowPX_DPT-956-2AAR25/tranmsitter low performance
23 May 2025HighPX_DPT-956-2AInstall scaffolding at DPT-956-2A
20 May 2025LowPX_PIT-1063-22BInstall cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
03 Dec 20251201000030948Corrective
28 Nov 20251201000004062Corrective
27 Nov 20251201000004062Corrective
22 Nov 20251201000003186Corrective
21 Nov 20251201000003186Corrective