TRANSMITTER,TEMP,MODEL II719,SS304
Material 4100059274 · TRANSMITTER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100059274
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 109 d · P80 126 d
- Unit price
- Rp 15.9M
Recommendation
- 1.Forecast 1.7 EA/year: 1.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~109 days; expected demand during lead time 0.5.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 4.On hand 0 + on order 2 is at or below the reorder point: order 3 now.
- 5.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
- 7.ML early warning: 56% probability of demand in the next 90 days.
Proposed purchase requisition
3 EA
Rp 47.6M · order by 01 Oct 2026
Expected arrival ≈ 109 days
Long-leadML early warningSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 18 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.8%
stockout risk now 1%
Unit price
Rp 15.9M
PO history
ML early warning: 56% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 454 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 5 functional locations
2 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FIT-194 FLOW | A | 4 | 1 | 0.47 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
| PX_DPT-1723A PP-604C DP | S | 1 | 1 | 0.06 |
| PX_KT-875 TURBINE FOR KC-875 | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 109 ± 45 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 31 Aug 2026 | PR06 Regular replenishment | 2 | Rp 16.0M | 18 Dec 2026 open | 109 d |
| 06 Dec 2025 | PR04 Regular (other) | 1 | Rp 15.7M | 08 Jul 2026 | 214 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 09 Jan 2026 | Medium | PX_KT-202 | KT-202 governor valve hunting |
| 17 Sept 2025 | Medium | PX_KT-202 | Replace lamp as per PM finding |
| 06 Jul 2025 | Low | PX_KT-202 | KT-202 steam leak at gland |
| 24 Jun 2025 | Low | PX_FIT-194 | Replace lamp as per PM finding |
| 03 Jun 2025 | Low | PX_DPT-1723A | Install scaffolding at DPT-1723A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 04 Jul 2025 | 1 | 201000031005 | Corrective |