TRANSMITTER,TEMP,MODEL HI905,CS

Material 4100059301 · TRANSMITTER · Plant 1000

ALong-leadMonitorSlow-moving
Material
4100059301
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 3 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
139 d · P80 126 d
Unit price
Rp 11.6M

Recommendation

  • 1.Forecast 5.9 EA/year: 5.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~139 days; expected demand during lead time 2.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 15.
  • 4.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
12 / 2
next delivery 11 Jun 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 10
Rec. Max
15
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 11.6M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 325 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_DPT-340C-33
CL-104 DP
A100.06
PX_KT-447
TURBINE FOR KC-447
S1136.24
PY_LIT-431A
KC-891A LEVEL
S100.03

Lead time and procurement

Lead time 139 ± 45 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
09 Sept 2026PR01
Import / long-lead
2Rp 11.4M11 Jun 2027
open
275 d
14 Jan 2026PR06
Regular replenishment
1Rp 11.8M30 Jul 2026197 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland
14 Jan 2026MediumPX_KT-447Follow up after steam upset KT-447
21 Nov 2025MediumPX_KT-447Leak from packing
19 Nov 2025MediumPX_KT-447Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
10 Nov 20251201000026092Corrective
10 Nov 20252201000026092Corrective