TRANSMITTER,TEMP,SIZE LD492,NBR

Material 4100059616 · TRANSMITTER · Plant 1000

BLong-leadReorderCriticalStockout
Material
4100059616
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 4 FuncLocs A/B)
Supplier
PRIMA INDUSTRI SENTOSA PT
Lead time
75 d · P80 126 d
Unit price
Rp 9.1M

Recommendation

  • 1.Forecast 0.9 EA/year: 0.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~75 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Long lead time: 80% of deliveries took up to 126 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 27.2M · order by 01 Oct 2026
Expected arrival ≈ 75 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 16%
Unit price
Rp 9.1M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 330 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 171.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~37 days.

Installed on 4 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TIT-534D
HE-981 TEMPERATURE
B100.04
PX_LIT-895
LEVEL
C100.03
PX_PIT-1705A
PRESSURE
C100.04
PX_KT-624A
TURBINE FOR KC-624A
S132.39

Lead time and procurement

Lead time 75 ± 45 days (PO history + category, 1 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
27 Jul 2025PR06
Regular replenishment
2Rp 9.1M11 Oct 202576 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
07 Feb 2026MediumPX_KT-624AReplace lamp as per PM finding
17 Jun 2025MediumPX_KT-624A[MSI-B-25-SWV-127/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
05 Nov 20251201000033478Corrective