TRANSMITTER,TEMP,TYPE XP405,PTFE

Material 4100059992 · TRANSMITTER · Plant 1000

AReorderNormalSlow-moving
Material
4100059992
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
74 d · P80 126 d
Unit price
Rp 34.1M (est.)

Recommendation

  • 1.Forecast 2.1 EA/year: 2.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~74 days; expected demand during lead time 0.4.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 136.6M · order by 01 Oct 2026
Expected arrival ≈ 74 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.7%
stockout risk now 25%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 319 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PY_LIT-485
LEVEL
A141.75
PX_TIT-499C-42A
TEMPERATURE
B100.04
PX_FIT-1629-13A
FLOW
S100.04

Lead time and procurement

Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Aug 2026MediumPY_LIT-485Replace lamp as per PM finding
05 May 2026MediumPY_LIT-485AR25/tranmsitter low performance
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
29 Nov 2025HighPY_LIT-485AR25/tranmsitter low performance
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
13 Aug 2025MediumPY_LIT-485Leak from packing
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
16 Nov 20252201000026377Corrective
07 Aug 20251201000016556Corrective