TRANSMITTER,TEMP,TYPE XW845,MONEL

Material 4100060032 · TRANSMITTER · Plant 1000

AReduceNon-moving
Material
4100060032
Category
TRANSMITTER
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
74 d · P80 126 d
Unit price
Rp 34.1M (est.)

Recommendation

  • 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~74 days; expected demand during lead time 0.0.
  • 3.A 98.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 34 exceeds the level to keep (1) by 33.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
34 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.3%
stockout risk now 0%
Unit price
Rp 34.1M
Category + unit estimate
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 67.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 4 functional locations

3 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_FIT-512
FLUSHING OIL FLOW
A400.04
PX_FIT-1693A
FLOW
B110.04
PX_TIT-1088
TEMPERATURE
C100.04

Lead time and procurement

Lead time 74 ± 45 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Dec 2025LowPX_KT-460BKT-460B governor valve hunting
27 Jul 2025MediumPX_KT-460BFollow up after steam upset KT-460B
22 May 2025MediumPX_FIT-1693AAR25/tranmsitter low performance

Recent goods issues

Never issued in the 17-month history.