Sparely
DU

TRANSMITTER,TEMP,MODEL XX575,MONEL

Material 4100060738 · TRANSMITTER · Plant 1000

ALong-leadReduceExcess
Material
4100060738
Category
TRANSMITTER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
PRIMA INDUSTRI SENTOSA PT
Lead time
86 d · P80 137 d
Unit price
Rp 18.1M

Recommendation

  • 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~86 days; expected demand during lead time 0.2.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
  • 4.Stock 36 exceeds the level to keep (6) by 30.
  • 5.Long lead time: 80% of deliveries took up to 137 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
36 / 2
next delivery 09 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.7%
stockout risk now 0%
Unit price
Rp 18.1M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 291 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 254.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FIT-1489
PP-1194 INLET FLOW
A120.47
PX_PIT-1817D-52A
PRESSURE
S100.04

Lead time and procurement

Lead time 86 ± 47 days (PO history, 6 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
25 Jun 2026PR03
Regular replenishment
2Rp 18.7M09 Nov 2026
open
137 d
06 Jun 2026PR06
Regular replenishment
2Rp 18.3M19 Jul 202643 d
27 Apr 2026PR03
Regular replenishment
1Rp 18.0M12 Aug 2026107 d
12 Apr 2026PR03
Regular replenishment
1Rp 18.0M01 Jun 202650 d
15 Oct 2025PR06
Regular replenishment
3Rp 18.2M13 Dec 202559 d
25 Jul 2025PR01
Import / long-lead
2Rp 17.6M29 Dec 2025157 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jun 2026EmergencyPX_FIT-1489Replace lamp as per PM finding
13 May 2025MediumPX_FIT-1489[MSI-B-25-UTF-163] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
28 Jul 20261203000004330Turnaround
25 Jul 20261203000004330Turnaround
14 Dec 20253201000028033Corrective