TRANSMITTER,TEMP,MODEL XX575,MONEL
Material 4100060738 · TRANSMITTER · Plant 1000
ALong-leadReduceExcess
- Material
- 4100060738
- Category
- TRANSMITTER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 2 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 86 d · P80 137 d
- Unit price
- Rp 18.1M
Recommendation
- 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~86 days; expected demand during lead time 0.2.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.Stock 36 exceeds the level to keep (6) by 30.
- 5.Long lead time: 80% of deliveries took up to 137 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
36 / 2
next delivery 09 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.7%
stockout risk now 0%
Unit price
Rp 18.1M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 291 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 254.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 2 functional locations
1 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FIT-1489 PP-1194 INLET FLOW | A | 1 | 2 | 0.47 |
| PX_PIT-1817D-52A PRESSURE | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 86 ± 47 days (PO history, 6 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 25 Jun 2026 | PR03 Regular replenishment | 2 | Rp 18.7M | 09 Nov 2026 open | 137 d |
| 06 Jun 2026 | PR06 Regular replenishment | 2 | Rp 18.3M | 19 Jul 2026 | 43 d |
| 27 Apr 2026 | PR03 Regular replenishment | 1 | Rp 18.0M | 12 Aug 2026 | 107 d |
| 12 Apr 2026 | PR03 Regular replenishment | 1 | Rp 18.0M | 01 Jun 2026 | 50 d |
| 15 Oct 2025 | PR06 Regular replenishment | 3 | Rp 18.2M | 13 Dec 2025 | 59 d |
| 25 Jul 2025 | PR01 Import / long-lead | 2 | Rp 17.6M | 29 Dec 2025 | 157 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Jun 2026 | Emergency | PX_FIT-1489 | Replace lamp as per PM finding |
| 13 May 2025 | Medium | PX_FIT-1489 | [MSI-B-25-UTF-163] Permanent repair |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Jul 2026 | 1 | 203000004330 | Turnaround |
| 25 Jul 2026 | 1 | 203000004330 | Turnaround |
| 14 Dec 2025 | 3 | 201000028033 | Corrective |