THERMOCOUPLE,N-2ELMNT,8X2300LG
Material 4100060757 · THERMOCOUPLE · Plant 1000
ALong-leadReorderNormalBelow reorder point
- Material
- 4100060757
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (28 of 72 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 72 d · P80 120 d
- Unit price
- Rp 18.8M
Recommendation
- 1.Forecast 25 EA/year: 25 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~72 days; expected demand during lead time 4.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 17, order up to 22.
- 4.On hand 5 + on order 0 is at or below the reorder point: order 17 now.
- 5.Long lead time: 80% of deliveries took up to 120 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 72 FuncLoc(s), 28 of them criticality A/B.
- 7.ML early warning: 72% probability of demand in the next 90 days.
Proposed purchase requisition
17 EA
Rp 319.7M · order by 01 Oct 2026
Expected arrival ≈ 72 days
Long-leadML early warningConvert to Stock ItemSingle source
On hand / on order
5 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
17
safety stock 13
Rec. Max
22
order qty 5
Service level
99.9%
stockout risk now 49%
Unit price
Rp 18.8M
PO history
ML early warning: 72% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 152 days ago, 122 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 14.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 72 functional locations
28 with criticality A/B · 82 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_BF-106-COIL26 BURNER BF-106 | A | 1 | 3 | 0.87 |
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
Lead time and procurement
Lead time 72 ± 46 days (PO history, 3 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Aug 2026 | PR06 Regular replenishment | 1 | Rp 18.6M | 23 Sept 2026 | 27 d |
| 20 Feb 2026 | PR05 Project / turnaround | 1 | Rp 18.8M | 09 Jul 2026 | 139 d |
| 04 Oct 2025 | PR03 Regular replenishment | 1 | Rp 19.0M | 04 Jan 2026 | 92 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 May 2026 | 1 | 205000029794 | Other maintenance |
| 06 Mar 2026 | 1 | 201000036940 | Corrective |
| 13 Jan 2026 | 1 | 204000005380 | Preventive |
| 31 Dec 2025 | 1 | 201000019150 | Corrective |
| 28 Dec 2025 | 1 | 201000025505 | Corrective |
| 26 Nov 2025 | 1 | 206000038839 | Other maintenance |
| 05 Aug 2025 | 1 | 201000012259 | Corrective |