THERMOCOUPLE,K-1ELMNT,3.2X1900LG
Material 4100060882 · THERMOCOUPLE · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100060882
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 8 FuncLocs A/B)
- Supplier
- PERMATA INSTRUMEN INTERNASIONAL PT
- Lead time
- 76 d · P80 98 d
- Unit price
- Rp 7.5M
Recommendation
- 1.Forecast 26 EA/year: 26 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~76 days; expected demand during lead time 5.3.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 18, order up to 26.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 26 now.
- 5.Long lead time: 80% of deliveries took up to 98 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
26 EA
Rp 194.6M · order by 01 Oct 2026
Expected arrival ≈ 76 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
18
safety stock 13
Rec. Max
26
order qty 8
Service level
99.9%
stockout risk now 91%
Unit price
Rp 7.5M
PO history
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 249 days ago, 52 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 9.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 8 functional locations
4 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 4 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 1 | 23 | 9.01 |
| PX_TEL-1249B TEMPERATURE | A | 2 | 0 | 0.01 |
| PX_TEL-1939 TEMPERATURE | C | 1 | 2 | 0.44 |
| PX_TEL-1155 HE-1750C OUTLET | C | 1 | 0 | 0.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1 | 23 | 9.44 |
Lead time and procurement
Lead time 76 ± 36 days (PO history + category, 2 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 29 Oct 2025 | PR06 Regular replenishment | 1 | Rp 7.5M | 18 Jan 2026 | 81 d |
| 07 May 2025 | PR06 Regular replenishment | 2 | Rp 7.5M | 11 Sept 2025 | 127 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Jan 2026 | 2 | 201000033187 | Corrective |
| 12 Dec 2025 | 1 | 201000021360 | Corrective |