THERMOCOUPLE,N-1ELMNT,6.4X1300LG
Material 4100061082 · THERMOCOUPLE · Plant 1000
AReduceNon-moving
- Material
- 4100061082
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 9 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 57 d · P80 98 d
- Unit price
- Rp 6.4M (est.)
Recommendation
- 1.Forecast 2.9 EA/year: 2.9 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~57 days; expected demand during lead time 0.4.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.Stock 9 exceeds the level to keep (6) by 3.
- 5.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
9 / 0
no open PO
Today Min / Max
4 / 11
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 6.4M
Category + unit estimate
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 45 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 9 functional locations
6 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-104-BRN08 COIL OUTLET BF-104 | A | 1 | 2 | 1.30 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_TEL-1717A TEMPERATURE | B | 1 | 0 | 0.01 |
| PX_TEL-676C-33B TEMPERATURE | B | 1 | 0 | 0.01 |
| PY_TEL-1110A PP-610B BTM | C | 1 | 0 | 0.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 2 | 23 | 9.44 |
Lead time and procurement
Lead time 57 ± 36 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
Recent goods issues
Never issued in the 17-month history.