THERMOCOUPLE,K-2ELMNT,6.4X500LG
Material 4100061191 · THERMOCOUPLE · Plant 1000
ALong-leadReorderCriticalSlow-moving
- Material
- 4100061191
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- ANUGRAH TEKNOLOGI INTERNASIONAL PT
- Lead time
- 79 d · P80 125 d
- Unit price
- Rp 7.2M
Recommendation
- 1.Forecast 8.8 EA/year: 8.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~79 days; expected demand during lead time 1.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 12.
- 4.On hand 1 + on order 1 is at or below the reorder point: order 10 now.
- 5.Long lead time: 80% of deliveries took up to 125 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
10 EA
Rp 72.2M · order by 01 Oct 2026
Expected arrival ≈ 79 days
Long-leadSingle sourceOpen PO
On hand / on order
1 / 1
next delivery 07 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
12
order qty 5
Service level
99.9%
stockout risk now 29%
Unit price
Rp 7.2M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 355 days ago, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-101-QF25 BURNER BF-101 | C | 1 | 0 | 0.45 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 79 ± 39 days (PO history, 3 PO lines) · on-time 23%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Jun 2026 | PR04 Regular (other) | 1 | Rp 7.2M | 07 Nov 2026 open | 144 d |
| 16 Feb 2026 | PR03 Regular replenishment | 2 | Rp 7.1M | 23 May 2026 | 96 d |
| 23 Dec 2025 | PR03 Regular replenishment | 1 | Rp 7.3M | 21 Feb 2026 | 60 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 04 Sept 2026 | High | PX_BF-112 | Install scaffolding at BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 01 Sept 2026 | Medium | PX_BF-112 | Replace burner tip BF-112 |
| 31 Aug 2026 | Medium | PX_BF-112 | Install cover plate for MCP cracking |
| 17 Aug 2026 | Medium | PX_BF-112 | Painting BF-112 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Oct 2025 | 1 | 201000022818 | Corrective |