THERMOCOUPLE,J-1ELMNT,3.2X3500LG

Material 4100061222 · THERMOCOUPLE · Plant 1000

AReorderNormalSlow-moving
Material
4100061222
Category
THERMOCOUPLE
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 5 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
41 d · P80 37 d
Unit price
Rp 2.1M

Recommendation

  • 1.Forecast 2.7 EA/year: 2.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~41 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Installed on 5 FuncLoc(s), 1 of them criticality A/B.
  • 6.ML early warning: 39% probability of demand in the next 90 days.
Proposed purchase requisition
6 EA
Rp 12.4M · order by 01 Oct 2026
Expected arrival ≈ 41 days
ML early warningSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
100.0%
stockout risk now 21%
Unit price
Rp 2.1M
PO history
ML early warning: 39% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 220 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 5 functional locations

1 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1638
TEMPERATURE
A400.01
PX_TEL-1680
HE-812B BTM
C100.01
PX_TEL-670-59A
TEMPERATURE
C100.01
PX_KT-624A
TURBINE FOR KC-624A
S432.39
PX_TEL-1663A-28B
CRACKED GAS OUTLET BF-110
S120.87

Lead time and procurement

Lead time 41 ± 19 days (PO history, 6 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
10 May 2026PR03
Regular replenishment
1Rp 2.0M14 Jun 202635 d
09 Mar 2026PR04
Regular (other)
1Rp 2.1M10 Apr 202632 d
08 Nov 2025PR06
Regular replenishment
2Rp 2.0M21 Nov 202513 d
13 Oct 2025PR06
Regular replenishment
3Rp 2.1M26 Nov 202544 d
04 Sept 2025PR03
Regular replenishment
1Rp 2.1M10 Oct 202536 d
16 Aug 2025PR03
Regular replenishment
2Rp 2.0M22 Sept 202537 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
07 Feb 2026MediumPX_KT-624AReplace lamp as per PM finding
19 Oct 2025MediumPX_TEL-1663A-28BInstall cover plate for MCP cracking
29 Jun 2025MediumPX_TEL-1663A-28BRepair insulation TEL-1663A-28B
17 Jun 2025MediumPX_KT-624A[MSI-B-25-SWV-127/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
23 Feb 20262201000005996Corrective
31 Jan 20261204000034161Preventive
30 Jan 20261204000034161Preventive
28 Nov 20251201000005829Corrective