THERMOCOUPLE,J-2ELMNT,6.4X300LG

Material 4100061410 · THERMOCOUPLE · Plant 1000

AMonitorCritical insurance spare
Material
4100061410
Category
THERMOCOUPLE
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
57 d · P80 98 d
Unit price
Rp 6.4M (est.)

Recommendation

  • 1.Forecast 0.7 EA/year: 0.7 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~57 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 1%
Unit price
Rp 6.4M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 421.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 3 functional locations

1 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-109
CRACKING FURNACE BF-109
A22911.58
PX_KT-447
TURBINE FOR KC-447
S4136.24
PX_TEL-599-40B
VD-609 BTM
S100.01

Lead time and procurement

Lead time 57 ± 36 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Sept 2026MediumPX_BF-109Thermograph wall BF-109
13 Sept 2026MediumPX_BF-109Install scaffolding at BF-109
03 Sept 2026LowPX_BF-109Install scaffolding at BF-109
02 Sept 2026LowPX_BF-109Install cover plate for MCP cracking
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
16 Aug 2026MediumPX_BF-109Install cover plate BF-109
13 Jul 2026MediumPX_BF-109Cleaning burner BF-109
09 Jul 2026MediumPX_BF-109Thermograph wall BF-109
09 Jul 2026LowPX_BF-109Leak from packing
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.