THERMOCOUPLE,K-1ELMNT,6.4X3900LG
Material 4100061431 · THERMOCOUPLE · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100061431
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 6 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 66 d · P80 98 d
- Unit price
- Rp 4.2M
Recommendation
- 1.Forecast 7.9 EA/year: 7.9 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~66 days; expected demand during lead time 1.4.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
- 4.Long lead time: 80% of deliveries took up to 98 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
Long-leadConvert to Stock ItemSingle source
On hand / on order
9 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
12
order qty 6
Service level
99.9%
stockout risk now 0%
Unit price
Rp 4.2M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 21 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 6 functional locations
1 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_TEL-1321 TEMPERATURE | C | 1 | 1 | 0.01 |
| PX_BF-103-BRN06 CONVECTION SECTION | C | 1 | 0 | 0.45 |
| PX_TEL-806B TEMPERATURE | S | 1 | 2 | 0.87 |
| PX_BF-109-PD08 COIL OUTLET BF-109 | S | 1 | 0 | 0.45 |
| PX_TEL-1908-3A TEMPERATURE | S | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 66 ± 36 days (PO history + category, 1 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 May 2025 | PR03 Regular replenishment | 1 | Rp 4.2M | 31 Aug 2025 | 93 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 14 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 10 Sept 2026 | Medium | PX_BF-106 | Replace burner tip BF-106 |
| 08 Sept 2026 | Low | PX_BF-106 | Leak from packing |
| 08 Sept 2026 | Medium | PX_BF-106 | Painting BF-106 |
| 03 Sept 2026 | Medium | PX_BF-106 | Install cover plate for MCP cracking |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000000813 | Corrective |
| 18 May 2025 | 1 | 201000000502 | Corrective |