THERMOCOUPLE,J-2ELMNT,3.2X300LG
Material 4100061476 · THERMOCOUPLE · Plant 1000
ALong-leadMaintainHealthy
- Material
- 4100061476
- Category
- THERMOCOUPLE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- LANGIT MESINDO GLOBAL PT
- Lead time
- 51 d · P80 98 d
- Unit price
- Rp 1.7M
Recommendation
- 1.Forecast 42 EA/year: 42 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~51 days; expected demand during lead time 5.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 18, order up to 38.
- 4.Long lead time: 80% of deliveries took up to 98 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle source
On hand / on order
34 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
18
safety stock 13
Rec. Max
38
order qty 20
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.7M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 36 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 12.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
Lead time and procurement
Lead time 51 ± 36 days (PO history + category, 1 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 15 Feb 2026 | PR06 Regular replenishment | 1 | Rp 1.7M | 21 Mar 2026 | 34 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
| 13 Sept 2026 | Medium | PX_BF-105 | Thermograph wall BF-105 |
| 07 Sept 2026 | Low | PX_BF-102 | Thermograph wall BF-102 |
| 06 Sept 2026 | Medium | PX_BF-102 | Decoking follow up BF-102 |
| 06 Sept 2026 | Medium | PX_BF-105 | Repair insulation BF-105 |
| 03 Sept 2026 | Medium | PX_BF-102 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 2 | 201000029943 | Corrective |