THERMOCOUPLE,N-1ELMNT,8X700LG

Material 4100061994 · THERMOCOUPLE · Plant 1000

ALong-leadReduceNon-moving
Material
4100061994
Category
THERMOCOUPLE
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
PERMATA INDUSTRI JAYA PT
Lead time
81 d · P80 98 d
Unit price
Rp 8.8M

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~81 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 8 exceeds the level to keep (3) by 5.
  • 5.Long lead time: 80% of deliveries took up to 98 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
8 / 2
next delivery 07 Feb 2027
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 8.8M
PO history
ML early warning: 13% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 12 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 344.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 1 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A33814.58

Lead time and procurement

Lead time 81 ± 36 days (PO history + category, 1 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
06 Sept 2026PR03
Regular replenishment
2Rp 8.8M07 Feb 2027
open
154 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103
26 Aug 2026MediumPX_BF-103Replace lamp as per PM finding
26 Aug 2026MediumPX_BF-103Hot spot at convection BF-103
03 Aug 2026MediumPX_BF-103Install scaffolding at BF-103
24 Jul 2026MediumPX_BF-103Thermograph wall BF-103
23 Jul 2026EmergencyPX_BF-103Decoking follow up BF-103

Recent goods issues

Never issued in the 17-month history.