THERMOCOUPLE,J-2ELMNT,8X2400LG

Material 4100062300 · THERMOCOUPLE · Plant 1000

BReduceNon-moving
Material
4100062300
Category
THERMOCOUPLE
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
57 d · P80 98 d
Unit price
Rp 6.4M (est.)

Recommendation

  • 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~57 days; expected demand during lead time 0.0.
  • 3.A 97.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 3 exceeds the level to keep (1) by 2.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
97.9%
stockout risk now 0%
Unit price
Rp 6.4M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 19.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~27 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-109-PD11
COIL OUTLET BF-109
B100.45
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 57 ± 36 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
17 Sept 2025MediumPX_KT-202Replace lamp as per PM finding
06 Jul 2025LowPX_KT-202KT-202 steam leak at gland

Recent goods issues

Never issued in the 17-month history.