THERMOCOUPLE,K-2ELMNT,8X2300LG

Material 4100062407 · THERMOCOUPLE · Plant 1000

ALong-leadReduceSlow-moving
Material
4100062407
Category
THERMOCOUPLE
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
GUNUNG UTAMA LESTARI PT
Lead time
76 d · P80 100 d
Unit price
Rp 16.0M

Recommendation

  • 1.Forecast 0.5 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~76 days; expected demand during lead time 0.1.
  • 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Stock 4 exceeds the level to keep (2) by 2.
  • 5.Long lead time: 80% of deliveries took up to 100 days and the fastest seen in its category 27 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
4 / 2
next delivery 21 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.4%
stockout risk now 0%
Unit price
Rp 16.0M
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 478 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 302.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-513
TURBINE FOR KC-513
A121.53

Lead time and procurement

Lead time 76 ± 26 days (PO history, 6 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
22 Jul 2026PR03
Regular replenishment
2Rp 15.8M21 Oct 2026
open
91 d
31 May 2026PR04
Regular (other)
2Rp 17.0M22 Jul 202652 d
24 Dec 2025PR03
Regular replenishment
2Rp 16.1M16 Mar 202682 d
13 Dec 2025PR03
Regular replenishment
2Rp 16.8M07 Apr 2026115 d
22 Sept 2025PR03
Regular replenishment
2Rp 15.7M31 Dec 2025100 d
13 Aug 2025PR06
Regular replenishment
2Rp 15.8M26 Oct 202574 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 Jan 2026MediumPX_KT-513KT-513 governor valve hunting
03 May 2025MediumPX_KT-513KT-513 governor valve hunting

Recent goods issues

Posting dateQtyOrderOrder type
10 Jun 20251201000007157Corrective