THERMOWELL,MODEL IH758,MONEL

Material 4100062582 · THERMOWELL · Plant 1000

ALong-leadReduceSlow-moving
Material
4100062582
Category
THERMOWELL
Base unit
EA
MRP type
Non Stock
Criticality
A (4 of 16 FuncLocs A/B)
Supplier
SURYA ENERGI JAYA PT
Lead time
92 d · P80 135 d
Unit price
Rp 14.1M

Recommendation

  • 1.Forecast 4.4 EA/year: 4.4 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~92 days; expected demand during lead time 1.1.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 10.
  • 4.Stock 25 exceeds the level to keep (10) by 15.
  • 5.Long lead time: 80% of deliveries took up to 135 days and the fastest seen in its category 43 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 16 FuncLoc(s), 4 of them criticality A/B.
  • 7.ML early warning: 65% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 7Single sourceOpen PO
On hand / on order
25 / 13
next delivery 10 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
10
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 14.1M
PO history
ML early warning: 65% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 231 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (7 units) excluded from the baseline.

Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~43 days.

Installed on 16 functional locations

4 with criticality A/B · 24 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102-PD05
PEEP DOOR
A200.45
PX_TEL-1452-37A
PP-1325 BTM
A100.01
PX_TEL-421-46
TEMPERATURE
A200.01
PX_TEL-1832-44
VD-1610 OUTLET
B110.01
PX_BF-111-BRN18
CONVECTION SECTION
C120.87
PX_TEL-1043
CRACKED GAS OUTLET BF-103
C400.01
PX_TEL-405B-22A
TEMPERATURE
C100.01
PX_TEL-456
TEMPERATURE
C100.01
PX_TEL-903D-44A
CRACKED GAS OUTLET BF-102
C100.01
PY_TEL-1504
TEMPERATURE
C100.01
PX_BF-109-PD08
COIL OUTLET BF-109
S100.45
PX_TEL-1080
TEMPERATURE
S100.01

Lead time and procurement

Lead time 92 ± 48 days (PO history, 7 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
26 Jul 2026PR05
Project / turnaround
9Rp 14.1M01 Feb 2027
open
190 d
26 Jun 2026PR06
Regular replenishment
4Rp 14.8M08 Sept 202674 d
14 May 2026PR10
Other
4Rp 13.9M10 Oct 2026
open
149 d
06 Apr 2026PR06
Regular replenishment
9Rp 14.2M25 May 202649 d
16 Feb 2026PR06
Regular replenishment
6Rp 13.8M05 May 202678 d
14 Dec 2025PR04
Regular (other)
3Rp 14.1M02 Mar 202678 d
29 Jul 2025PR03
Regular replenishment
5Rp 14.9M02 Oct 202565 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Jun 2026LowPX_BF-111-BRN18Replace burner tip BF-111-BRN18
16 May 2025MediumPX_TEL-1832-44TEL-1832-44 abnormal indication
14 May 2025LowPX_BF-111-BRN18Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
12 Feb 20261206000018451Other maintenance
19 Jan 20262201000032798Corrective
17 Jan 20262201000004586Corrective
17 Jan 20261201000004586Corrective
20 Dec 20251201000018607Corrective
16 Dec 20252203000018502Turnaround
15 Dec 20251203000018502Turnaround
30 Nov 20251203000012255Turnaround
27 Nov 20251203000012255Turnaround
26 Nov 20252203000012255Turnaround
19 Aug 20251201000022145Corrective
08 Aug 20251201000036733Corrective
24 Jul 20252205000036740Other maintenance