THERMOWELL,TYPE DZ785,INCOLOY

Material 4100062652 · THERMOWELL · Plant 1000

BReduceExcess
Material
4100062652
Category
THERMOWELL
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
78 d · P80 140 d
Unit price
Rp 6.1M (est.)

Recommendation

  • 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~78 days; expected demand during lead time 0.2.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.Stock 106 exceeds the level to keep (4) by 102.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
106 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 6.1M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 91 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 260.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~43 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1323-44B
CRACKED GAS OUTLET BF-102
B100.01
PX_TEL-1637A-39B
VD-526 OUTLET
C100.01
PX_TEL-636-4
CRACKED GAS OUTLET BF-111
S100.01

Lead time and procurement

Lead time 78 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
02 Jul 20261201000025988Corrective
25 Jun 20261201000031485Corrective