Sparely
DU

THERMOWELL,SIZE PZ61,SS316

Material 4100062824 · THERMOWELL · Plant 1000

ALong-leadReduceSlow-moving
Material
4100062824
Category
THERMOWELL
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
GUNUNG UTAMA LESTARI PT
Lead time
62 d · P80 140 d
Unit price
Rp 2.9M

Recommendation

  • 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~62 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.Stock 13 exceeds the level to keep (10) by 3.
  • 5.Long lead time: 80% of deliveries took up to 140 days and the fastest seen in its category 43 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
13 / 1
next delivery 12 Oct 2026
Today Min / Max
6 / 13
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
99.9%
stockout risk now 0%
Unit price
Rp 2.9M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 278 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 176.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~43 days.

Installed on 2 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TEL-1244D
PP-1864 BTM
A300.01
PX_TEL-1441
TEMPERATURE
S100.01

Lead time and procurement

Lead time 62 ± 40 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
16 Aug 2026PR03
Regular replenishment
1Rp 2.9M12 Oct 2026
open
57 d
08 Jul 2025PR03
Regular replenishment
1Rp 2.9M29 Jul 202521 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
27 Dec 20251201000037985Corrective
27 Dec 20254201000037985Corrective