THERMOWELL,SIZE XO292,MONEL
Material 4100063480 · THERMOWELL · Plant 1000
- Material
- 4100063480
- Category
- THERMOWELL
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 78 d · P80 140 d
- Unit price
- Rp 6.1M (est.)
Recommendation
- 1.Forecast 0.1 EA/year: 0.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~78 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 2 exceeds the level to keep (0) by 2.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 323,967/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~43 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TEL-298A PP-821 BTM | S | 1 | 0 | 0.01 |
Lead time and procurement
Lead time 78 ± 40 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 Sept 2025 | 1 | 201000026249 | Corrective |