GAUGE,PRESSURE,0-100KG/CM2,4IN DIAL
Material 4100064414 · GAUGE · Plant 1000
AMaintainHealthy
- Material
- 4100064414
- Category
- GAUGE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 30 d · P80 31 d
- Unit price
- Rp 4.9M
Recommendation
- 1.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~30 days; expected demand during lead time 0.1.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 4.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Single sourceSame description as 1 other material number
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 4.9M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 54 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 425.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_PGI-673B PRESSURE GAUGE | A | 1 | 0 | 0.02 |
| PX_PGI-281-55A PP-319 BTM | C | 1 | 0 | 0.02 |
| PX_PGI-636A HE-1188D DISCHARGE | C | 1 | 0 | 0.02 |
Lead time and procurement
Lead time 30 ± 16 days (PO history, 3 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Jun 2026 | PR01 Import / long-lead | 2 | Rp 4.9M | 20 Jul 2026 | 28 d |
| 30 Apr 2026 | PR03 Regular replenishment | 2 | Rp 4.7M | 02 Jun 2026 | 33 d |
| 02 Dec 2025 | PR06 Regular replenishment | 2 | Rp 4.9M | 19 Dec 2025 | 17 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Aug 2026 | 1 | 202000039090 | Emergency |
| 21 Jul 2026 | 1 | 204000012433 | Preventive |