SPRING,SAFETY VALVE,SIZE QV915,NBR
Material 4100066098 · SPRING · Plant 1000
ASafety-criticalLong-leadReorderCriticalStockout
- Material
- 4100066098
- Category
- SPRING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (9 of 35 FuncLocs A/B, 25 safety/shutdown valve)
- Supplier
- SURYA ENERGI JAYA PT
- Lead time
- 129 d · P80 142 d
- Unit price
- Rp 11.4M
Recommendation
- 1.Safety-critical element: installed on 25 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 8.1 EA/year: 8.1 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~129 days; expected demand during lead time 2.9.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 14.
- 5.On hand 0 + on order 4 is at or below the reorder point: order 10 now.
- 6.Long lead time: 80% of deliveries took up to 142 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 35 FuncLoc(s), 9 of them criticality A/B.
- 8.ML early warning: 54% probability of demand in the next 90 days.
Proposed purchase requisition
10 EA
Rp 114.0M · order by 01 Oct 2026
Expected arrival ≈ 129 days
Safety-critical (SCE)Long-leadML early warningConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 4
next delivery 29 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 8
Rec. Max
14
order qty 4
Service level
99.9%
stockout risk now 34%
Unit price
Rp 11.4M
PO history
ML early warning: 54% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 4 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 9.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.
Installed on 35 functional locations
9 with criticality A/B · 47 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 4 | 7 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PY_PRV-1236A SAFETY VALVE HE-621 | A | 1 | 2 | 0.47 |
| PX_PRV-403A SAFETY VALVE HE-532A | A | 1 | 1 | 0.47 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_PRV-708C SAFETY VALVE HE-179D | A | 1 | 0 | 0.04 |
| PX_PRV-1456 SAFETY VALVE HE-308C | B | 1 | 1 | 0.04 |
| PX_PRV-276A SAFETY VALVE PP-1657A | B | 1 | 0 | 0.04 |
| PX_PRV-1028 SAFETY VALVE VD-727 | C | 4 | 0 | 0.04 |
| PX_PRV-997A SAFETY VALVE BF-105 | C | 1 | 0 | 0.04 |
| PX_KT-383A TURBINE FOR KC-383A | S | 2 | 7 | 3.67 |
Lead time and procurement
Lead time 129 ± 56 days (PO history, 4 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Sept 2026 | PR06 Regular replenishment | 2 | Rp 11.2M | 11 Dec 2026 open | 88 d |
| 18 May 2026 | PR06 Regular replenishment | 2 | Rp 11.6M | 29 Nov 2026 open | 195 d |
| 25 Nov 2025 | PR04 Regular (other) | 3 | Rp 11.0M | 08 Mar 2026 | 103 d |
| 30 May 2025 | PR06 Regular replenishment | 3 | Rp 11.7M | 14 Sept 2025 | 107 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Sept 2026 | 1 | 206000026719 | Other maintenance |
| 24 Apr 2026 | 2 | 201000027196 | Corrective |
| 31 Jan 2026 | 1 | 201000026900 | Corrective |
| 24 Dec 2025 | 2 | 201000003244 | Corrective |
| 26 May 2025 | 1 | 201000000928 | Corrective |