Sparely
DU

SPRING,SAFETY VALVE,MODEL DW505,CS

Material 4100066099 · SPRING · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100066099
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
A (5 of 13 FuncLocs A/B, 8 safety/shutdown valve)
Supplier
No PO history
Lead time
137 d · P80 196 d
Unit price
Rp 8.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 8 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 5.1 EA/year: 5.1 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~137 days; expected demand during lead time 1.9.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 10.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 10 now.
  • 6.Installed on 13 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
10 EA
Rp 88.2M · order by 01 Oct 2026
Expected arrival ≈ 137 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
10
order qty 3
Service level
99.9%
stockout risk now 85%
Unit price
Rp 8.8M
Category + unit estimate
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 243 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 13 functional locations

5 with criticality A/B · 17 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_PRV-1881C
SAFETY VALVE PP-837
A210.47
PX_PRV-1300
SAFETY VALVE HE-874B
A100.04
PX_PRV-1506C
SAFETY VALVE VD-1990B
A100.04
PX_PRV-1154B
SAFETY VALVE PP-1765B
C100.04
PX_PRV-331B
SAFETY VALVE HE-826A
C100.04
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-202
TURBINE FOR KC-202
S142.81
PX_KT-624A
TURBINE FOR KC-624A
S432.39
PX_PRV-108C
SAFETY VALVE HE-1181C
S100.04
PX_PRV-1201
SAFETY VALVE HE-1502B
S100.04

Lead time and procurement

Lead time 137 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A

Recent goods issues

Posting dateQtyOrderOrder type
31 Jan 20261201000018506Corrective